Free CAPM Exam Braindumps
Certified Associate in Project Management (PMI-100) Questions 476–480 (page: 97)

Updated On: 9-Feb-2026

Which is a communication method used in the Report Performance process?

  1. Expert judgment
  2. Project management methodology
  3. Stakeholder analysis
  4. Status review meetings

Answer(s): D



Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

  1. Monitor and Control Risks
  2. Plan Risk Management
  3. Perform Qualitative Risk Analysis
  4. Perform Quantitative Risk Analysis

Answer(s): C



In which process is a project manager identified and given the authority to apply resources to project activities?

  1. Acquire Project Team
  2. Develop Project Management Plan
  3. Manage Project Execution
  4. Develop Project Charter

Answer(s): D

Explanation:

Process: 4.1. Develop Project Charter
Definition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.

Inputs
1. Project statement of work
2. Business case
3. Agreements
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Facilitation techniques

Outputs
1. Project charter



Which of the following documents allows the project manager to assess risks that may require near term action?

  1. Probability and impact matrix
  2. Contingency analysis report
  3. Risk urgency assessment
  4. Rolling wave plan

Answer(s): C

Explanation:

11.3.2.5 Risk Urgency Assessment
Risks requiring near-term responses may be considered more urgent to address. Indicators of priority may include probability of detecting the risk, time to affect a risk response, symptoms and warning signs, and the risk rating. In some qualitative analyses, the assessment of risk urgency is combined with the risk ranking that is determined from the probability and impact matrix to give a final risk severity rating.



Which activity involves ensuring that the composition of a projects configuration items is correct?

  1. Configuration Identification
  2. Configuration Status Accounting
  3. Configuration Verification and Audit
  4. Configuration Quality Assurance

Answer(s): C

Explanation:

Configuration identification. Identification and selection of a configuration item to provide the basis for which the product configuration is defined and verified, products and documents are labeled, changes are managed, and accountability is maintained.
Configuration status accounting. Information is recorded and reported as to when appropriate data about the configuration item should be provided. This information includes a listing of approved configuration identification, status of proposed changes to the configuration, and the implementation status of approved changes.

Configuration verification and audit. Configuration verification and configuration audits ensure the composition of a project’s configuration items is correct and that corresponding changes are registered, assessed, approved, tracked, and correctly implemented. This ensures the functional requirements defined in the configuration documentation have been met.



Viewing page 97 of 222
Viewing questions 481 - 485 out of 1320 questions


Post your Comments and Discuss PMI CAPM exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!