Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

  1. Plan Risk Responses
  2. Manage Stakeholder Expectations
  3. Define Scope
  4. Report Performance

Answer(s): B



Which process involves identifying and documenting the logical relationships between project activities?

  1. Develop Schedule
  2. Sequence Activities
  3. Create WBS
  4. Applying leads and lags

Answer(s): B

Explanation:

Process: 6.3 Sequence Activities
Definition: The process of identifying and documenting relationships among the project activities. Key Benefit: The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Milestone list
5. Project scope statement
6. Enterprise environmental factors
7. Organizational process assets

Tools & Techniques
1. Precedence diagramming method (PDM)
2. Dependency determination
3. Leads and lags

Outputs
1. Project schedule network diagrams
2. Project documents updates



Which of the following is an example of the simplest fixed-price contract?

  1. Purchase requisition
  2. Purchase order
  3. Verbal agreement
  4. Request for quote

Answer(s): B



Which technique helps to determine the risks that have the most potential impact on a project?

  1. Cost risk simulation analysis
  2. Expected monetary value analysis
  3. Modeling and simulation
  4. Sensitivity analysis

Answer(s): D

Explanation:

11.4.2.2 Quantitative Risk Analysis and Modeling Techniques
Commonly used techniques use both event-oriented and project-oriented analysis approaches, including:

• Sensitivity analysis. Sensitivity analysis helps to determine which risks have the most potential impact on the project. It helps to understand how the variations in project’s objectives correlate with variations in different uncertainties. Conversely, it examines the extent to which the uncertainty of each project element affects the objective being studied when all other uncertain elements are held at their baseline values.



Labor, materials, equipment, and supplies are examples of:

  1. Resource attributes.
  2. Resource types.
  3. Resource categories.
  4. Resource breakdown structures (RBS).

Answer(s): C

Explanation:

6.4.3.2 Resource Breakdown Structure
The resource breakdown structure is a hierarchical representation of resources by category and type. Examples of resource categories include labor, material, equipment, and supplies. Resource types may include the skill level, grade level, or other information as appropriate to the project. The resource breakdown structure is useful for organizing and reporting project schedule data with resource utilization information.