How is the schedule variance calculated using the earned value technique?

  1. EV less AC
  2. AC less PV
  3. EV less PV
  4. AC less EV

Answer(s): C



Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

  1. Control chart
  2. Flowchart
  3. Run chart
  4. Pareto chart

Answer(s): B



Which type of analysis is used as a general management technique within the Plan Procurements process?

  1. Risk assessment analysis
  2. Make or buy analysis
  3. Contract value analysis
  4. Cost impact analysis

Answer(s): B



Which of the following tools and techniques is used in the Verify Scope process?

  1. Inspection
  2. Variance analysis
  3. Expert judgment
  4. Decomposition

Answer(s): A



Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

  1. Project Time Management
  2. Project Cost Management
  3. Project Scope Management
  4. Project Human Resource Management

Answer(s): A