Who prepares the statement of work (SOW) for external projects?

  1. Customer
  2. Project management team
  3. Project Manager
  4. Chief Financial Officer (CFO)

Answer(s): A



You are the program manager for your organization. Your current program, which has just been initiated, needs to launch several projects in order to create all of the benefits of the program. What document do you need to create in order to initiate the projects within your program?

  1. Project charter
  2. Program charter
  3. Program scope statement
  4. Project preliminary scope statement

Answer(s): A



You are the program manager for your organization. You're currently creating an accountability matrix starting with yourself, the program manager and the program sponsor. What program management process identifies the program sponsor?

  1. Pre-program setup phase
  2. Authorization of program processes and projects
  3. Initiate program process
  4. Initiation of the program management team

Answer(s): C



You are the program manager for your organization. Management has asked you to create a method to track the program stakeholders' concerns, threats, and demands for communication. They would like you to map out each stakeholder or stakeholder group and identify trends within the chart to help your program communicate better. What type of a chart should you create for management?

  1. RACI chart
  2. Stakeholder analysis chart
  3. Roles and responsibilities chart
  4. Communication matrix

Answer(s): B