You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance data.
In which of the following processes are you working on?

  1. Plan Communication
  2. Distribute Information
  3. Report Program Performance
  4. Monitor and Control Program Performance

Answer(s): C



You are the program manager for your organization and are working with your team to identify stakeholders in the program. Where should the identified stakeholders and their information be recorded?

  1. Stakeholder matrix
  2. Communications management plan
  3. Requirements traceability matrix
  4. Stakeholder registry

Answer(s): D



Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?

  1. Deadlines for project milestones
  2. Building codes
  3. A predetermined program budget
  4. Weather

Answer(s): D



Identify the term described in the statement given below? "The use of it should be reviewed along with an assessment of their effectiveness. This will aid the program management in determining if risks to the program are being effectively managed. It also provides feedback to the program management on any projects that need to be recovered or terminated."

  1. Budget
  2. Planned Value
  3. Contingency Reserve
  4. Earned Value

Answer(s): C



You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

  1. Monitor and Control Program Scope
  2. Monitor and Control Project Performance
  3. Monitor and Control Program Schedule
  4. Manage Program Issues

Answer(s): B



Viewing page 42 of 126
Viewing questions 206 - 210 out of 713 questions