A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.
What should the team do?

  1. Estimate only functional requirements that will impact product quality
  2. Add team resources
  3. Refer the issue tot eh product owner
  4. Break non-functional requirements into those that can be delivered in the given sprint

Answer(s): C



A development team and product owner disagrees on a user story in the product backlog.
What should the agile practitioner do?

  1. Have the development team follow the product owner's direction
  2. Openly challenge the product owner in the effort to poke holes in their approach
  3. Facilitate a conversation about the user story between the development team and the product owner
  4. Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

Answer(s): C



During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points.
How should this be handled?

  1. The story should be assigned eight story points as per the majority vote
  2. The story should be added to the backlog and reassessed later
  3. The story should be assigned points after a discussion with the fifth team member to see if a consensus can be reached
  4. The decision for the number of story points should be made by the customer

Answer(s): C



A project is starting and the type of work is complex and suitable for agile. In assessing the team members, it appears that co-location would be a challenge.
What should the agile practitioner do?

  1. Select and implement collaboration tools to augment team interactions
  2. Provide each geographical area with their own product owner and divide the work between the teams
  3. Increase the number of requirements documents and ensure they are clearly communicated
  4. After several sprints, calculate velocity based on primary team location and use secondary team as reserve

Answer(s): A



Page 16 of 81



Post your Comments and Discuss PMI PMI-ACP exam with other Community members:

mustapha commented on August 14, 2024
good simulation
Anonymous
upvote

Ravi commented on March 28, 2024
I am from India. I wrote this exam last week and I passed. The study material is good. Saved me a lot of time. I was actually planning on a bootcamp but then I came across this site and decided to give a try. It worked out well.
INDIA
upvote

Krasen commented on June 15, 2023
Thank you for these questions and answers. The 50% discount code worked. I bouth 2 exams and I already passed one.
HONG KONG
upvote

Adam K commented on May 24, 2023
The stuff is really good. I do recommend it.
POLAND
upvote

Herath commented on March 18, 2022
I am happy to report that I passed my second exam today. Thank you guys for this helpful study package.
SINGAPORE
upvote

BBQ commented on December 30, 2021
It is a very useful information before going to your actual exam.
HONG KONG
upvote

Kristopher commented on January 27, 2019
I loved the payment part of the website. They do not ask for any personal information. Just the credit card number and date. Very desecrate. I like!
UNITED KINGDOM
upvote

Ivan Cheung commented on August 23, 2016
The material is useful and save me a lot of time to get the exam passed without any difficulty!!
HONG KONG
upvote