An agile project leader is delivering a team kick-off session. The first exercise is a `Life Timeline` `" a story-telling exercise where each team member tells their life story, explains how they experienced the highs and lows of their journey, and identifies their fears and hopes.
What is the project leader trying to create?

  1. A safe space for team members to learn to trust one another, leading to collaborative relationships
  2. A safe space to team members to learn to be vulnerable, leading to high performance relationships
  3. A safe space for team members to learn to share, leading to collaborative relationship
  4. A safe space for team members to learn about each other's weaknesses and strengths

Answer(s): A



The project team is ahead of schedule and beginning to gold-plate the feature included in the current sprint.
What should the agile project manager do?

  1. Since the team has extra time, notify the product owner and secure approval for the extra work on this feature
  2. Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now
  3. Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration
  4. Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog

Answer(s): D



During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay.
What should the scrum master advise the team do?

  1. Implement the story since the team is running behind schedule
  2. Create a spike to finalize the story's technical approach
  3. Transfer the story to a scrum team experienced in solving similar problem
  4. Ask the product owner to reduce the story's priority and wait until more technical details are available

Answer(s): B



During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good.
What should the agile team lead do?

  1. Require the team to try only those ideas that will ensure success
  2. Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives
  3. Associate idea successes and failures with the team's incentive plan to ensure accountability
  4. Encourage the team to try the ideas, even if failure may be the outcome

Answer(s): D



What is the first thing an agile development team should do when planning an iteration?

  1. Assign the tasks to one team member
  2. Separate the stories into tasks
  3. Estimate the stories' tasks
  4. Help establish the next sprint's goal

Answer(s): B