Free PMI-ACP Exam Braindumps (page: 23)

Page 22 of 81

An agile project manager notices that the product manager manages team member's day-to-day tasks in a way that distracts them from their core responsibilities.
In addition, the team believes that their questions on product backlog prioritization are not being answered on time.
What should the agile practitioner do?

  1. Discuss and address this in the iteration retrospective
  2. Let the product owner know it is the project manager's responsibility to drive a ream's tasks
  3. Discuss the roles and responsibilities of the project team with the product owner
  4. Ask the product owner to work extra hours to answer the team's questions

Answer(s): A



An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager.
What should the scrum master do?

  1. Dismiss the team member
  2. Discuss the situation with the functional manager
  3. Report the functional manager to the project sponsor
  4. Demand that the functional manager respect the project charter

Answer(s): B



During a mature agile team's planning meeting, a team member proposes a new framework that would considerably reduce implementation time. However, the team lacks the confidence to try the new framework.
To help the team gain confidence, what should the agile practitioner suggest?

  1. Develop a spike
  2. Create an Ishikawa diagram
  3. Perform a pre-mortem analysis
  4. Complete a variance and trend analysis

Answer(s): A



The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration.
What must the agile practitioner do?

  1. Add the new change request as a new user story in the product backlog for the upcoming iteration
  2. Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value
  3. Recommend cancelling the current iteration and plan the change request into the next iteration
  4. Recommend that the product owner add this change request as a user story to the backlog for the current iteration

Answer(s): B






Post your Comments and Discuss PMI PMI-ACP exam with other Community members:

PMI-ACP Discussions & Posts