An agile practitioner wants to ensure that stakeholders have current information about a project's progress.
What should the agile practitioner do?

  1. Regularly circulate an updated, detailed version of the project plan
  2. Frequently update the online project management office (PMO) repository site
  3. Invite the stakeholders to daily stand ups
  4. Post a project board in an area where all can view it

Answer(s): D



A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing its teams.
What strategy should be employed to re-organize the teams?

  1. All the teams from both products should be simultaneously called together and allowed to completely self-manage
  2. Teams that worked on similar components in the separate products should be combined to minimize disruption and capitalize on synergies
  3. After grouping individuals by role, multi-discipline teams should be created that are comprised of one member from each role
  4. Features should be prioritized and then teams should be organized around those priorities

Answer(s): A



A client states that a product is not being built as requested.
How should the agile team address this?

  1. Conduct an internal review to validate functionality before shipping
  2. Audit the quality control process to ensure that the product adheres to requirements
  3. Lengthen iterations to ensure there is sufficient time to build functionality
  4. Hold product review sessions with the client to obtain product acceptance

Answer(s): D



A new product owner shares the product vision during the team launch event. The team asks for clarification on the product roadmap and its high-level features.
What should the product owner do?

  1. Determine the required tasks for implementing the high-level features
  2. Identify the detailed design for the high-level features
  3. Prioritize the product backlog for the upcoming release
  4. Estimate the user stories in the iteration backlog

Answer(s): C