PMI PMI-ACP Exam Questions
PMI Agile Certified Practitioner (Page 7 )

Updated On: 27-Feb-2026

A team is transitioning from a predictive approach to an agile approach. Historically, the team has delivered work products that did not meet customer expectations.
What agile practice can help the team to alleviate this?

  1. Test-driven development (TDD)
  2. Clear definition of done and regular demos
  3. Collaborative team planning games
  4. Consistent team velocity

Answer(s): B



A team member on a scrum project previously provided support to another application. Due to this with that application, the team member's former supervisor continues assigning them tasks related to that project. The new project's scrum master includes these issues in the risk register.
What should the scrum master do next?

  1. Monitor the threats and risks while allowing the team member to multitask on both projects
  2. Assign more resources to the sprints to compensate for the absence of the team member
  3. Ensure that the threats and risks are communicated and addressed
  4. Assign fewer stories to the sprints so that the team member can still meet sprint goals

Answer(s): C



An organization initiates a pilot project to introduce agile methodology for the successful delivery of projects.
What should the project manager do to share this project's knowledge and learning with wider organizational business groups?

  1. Invite people from across the organization to attend daily stand ups
  2. Invite people from across the organization to attend retrospectives
  3. Invite people from across the organization to attend the release meeting and project retrospectives
  4. Regularly meet with people across the organization to share the project's lessons learned and best practices

Answer(s): D



A project team identifies a number of technical challenges with features in the next sprint.
What should they do?

  1. Request direction from the technical manager
  2. Encourage that product owner to reallocate the features to another sprint
  3. Determine who is best qualified to address the challenges
  4. Ask the product owner to assign the tasks to the most appropriately skilled resources

Answer(s): C



The team is refining user stories during the backlog grooming session and confused on the acceptance criteria and level of details.
What should the agile practitioner do?

  1. Complete the test cases before creating the story in the backlog
  2. Define the detailed business requirements so that the team can continue with development
  3. Define the user stories with just enough details so the team can collaborate continuously
  4. Ensure the acceptance criteria includes testing scenarios, so the team can do through testing

Answer(s): C