Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project.
When Holly crashes the project what project document must be updated to reflect this change to the approach?

  1. Develop schedule process
  2. Risk register
  3. Project risk management plan
  4. Activity attributes

Answer(s): D

Explanation:

When Holly adds resources to the project, as in this instance, she will need to update the activity attributes to reflect the new labor. Activity attributes are an output of the Define Activity process. These attributes refer to the multiple components that frame up an activity. The components for each activity during the early stages of the project are the Activity ID, WBS ID, and Activity name. At the later stages, the activity attributes include Activity codes, Predecessor activity, activity description, logical relationship, successor activity, leads and lags, imposed dates, and constraints and assumptions. Activity attributes are used for schedule development and for ordering, selecting, and sorting the planned schedule activities in a number of ways within reports. In project document updates, activity attributes are updated to include any revised resource requirements and other revision generated by the develop schedule process.



Examine the figure given below: Which path is considered the critical path?

  1. ACDFJ
  2. ACGIJ
  3. ABEFJ
  4. ABDFJ

Answer(s): B

Explanation:

The critical path is the path in the project network diagram with the longest duration. In project management, a critical path is the sequence of project network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). In this instance path ACGIJ is the longest as it takes 23 days.

Answer options C and D are incorrect. These paths take 13 days.
Answer option A is incorrect. This path only takes 19 days.



Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis.
What other tool Winnie can use to help and generate an updated project schedule?

  1. Critical path method
  2. Schedule management plan
  3. Scheduling tool
  4. Critical chain method

Answer(s): C

Explanation:

The scheduling tool is the only other tool that can help Winnie to create an updated project schedule. The scheduling tool is used in combination with manual methods or further project management software to carry out the schedule network analysis to produce an updated project schedule.
Answer option A is incorrect. The critical path method can be analyzed, but it is a part of the project management information system. In addition, the critical path is not better or worse than the critical chain method so by having both answers among the choices both answers are cancelled.
Answer option D is incorrect. The critical chain method can be analyzed, but it is the part of the project management information system. In addition, the critical path is not better or worse than the critical path method so by having both answers among the choices both answers are cancelled.
Answer option B is incorrect. The schedule management plan may need to be referenced to create a new project schedule, but it is not a tool that Winnie can use.



You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion.
What is the estimate at completion for this project that you will need to report to management?

  1. -$62,922.80
  2. $1,312,504
  3. $1,525,000
  4. $787,504

Answer(s): B

Explanation:

The estimate at completion can be calculated by dividing the budget at completion by the cost performance index. Here, CPI =EV/AC=(0.40*1,258,456)/525000 = 0.95882 EAC = BAC/CPI = 1,258456/0.95882 = 1,312,504 What is Estimate at Completion (EAC)? Estimate at Completion (EAC) is a field that displays the final cost of the project including the actual costs and the forecast of remaining costs based on the cost performance index (CPI) so far. The formula used to calculate this estimate is as follows: ACWP+(BAC-BCWP)/CPI
Answer option D is incorrect. $787,504 is the estimate to complete.
Answer option A is incorrect. -$62,922.80 is the schedule variance.
Answer option C is incorrect. This is not a valid calculation for this question.



Page 10 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Manish commented on October 19, 2024
Hi it's a good initiative
Anonymous
upvote

Veronica commented on October 19, 2024
Brain dump questions are new to me...I'm not sure how to respond to this since I only answered a handful of questions
UNITED STATES
upvote

Kamran commented on October 19, 2024
Useful resource
UNITED STATES
upvote

AC commented on October 19, 2024
For a moment no, comment, still moving well
Anonymous
upvote

johnny commented on October 19, 2024
great insight
Anonymous
upvote

Marc commented on October 18, 2024
What the best way to learn terraform?
UNITED STATES
upvote

murad commented on October 18, 2024
Very helpful for certs
JORDAN
upvote

Jack commented on October 18, 2024
are these legit ?
Anonymous
upvote

Juan commented on October 18, 2024
From until what page number is enough to pass the certification?
Anonymous
upvote

Sandeep commented on October 18, 2024
This is very helpful for exam crack
UNITED STATES
upvote

Cheron commented on October 18, 2024
Before all i thank to you for your support. I passed my 2 exams I purchased with full version. I got 90% in one exam and in 2 exam I got 86%.
Anonymous
upvote

LA commented on October 18, 2024
Hi there, I have scheduled my EXAM and will share my experience if these questions are valid or not.
Anonymous
upvote

Mazin commented on October 18, 2024
Good questions
Anonymous
upvote

Test commented on October 18, 2024
Test are these teak answeres?
Anonymous
upvote

anonymous commented on October 17, 2024
can someone tell me if this is real questions
UNITED STATES
upvote

Steven commented on October 17, 2024
Questions are spot on and I passed the exam.
UNITED STATES
upvote

Ntombi commented on October 17, 2024
i find the questions helpful for my exam preparation
Anonymous
upvote

Ntombi commented on October 17, 2024
The questions help me to see if I understood what I have learned
Anonymous
upvote

ntombi commented on October 17, 2024
writing exam at the end of the month
Anonymous
upvote

Apvj commented on October 17, 2024
Need to update section 5 questions,it was all new question today in exam , unitl section 4 it was fine even though pattern of question changed
Anonymous
upvote

ghada commented on October 17, 2024
it helps a lot
Anonymous
upvote

John commented on October 17, 2024
Good mock exam
Anonymous
upvote

test commented on October 17, 2024
Good content
UNITED STATES
upvote

Manoo commented on October 17, 2024
Hello guys, I hope everyone is doing good and preparing for this exam. I just wanted to share my experience about my exam. I wrote this exam yesterday and I passed. The key is to focus on each topic and memorize all these questions. You see most of them in your test. Good luck
INDIA
upvote

Ad commented on October 17, 2024
Hi I am new to IT
Anonymous
upvote

sadai commented on October 17, 2024
I really apricate this helpful test thank you so much
Anonymous
upvote

Lee commented on October 17, 2024
This is a very good resource. I'm glad this is provided for free for everyone to pass their exam. I'm sure everyone knows how difficult these exams are.
UNITED STATES
upvote

BANKEY BIHARI LAL commented on October 17, 2024
Very good mock exams as per the actual exam standards.
INDIA
upvote

Faruk commented on October 17, 2024
is free content is enough for pas az-900 ?
Anonymous
upvote

chad johnson commented on October 16, 2024
learning from this test
UNITED STATES
upvote

Keketso commented on October 16, 2024
This is a valuable resource for Az-900, i think
Anonymous
upvote

MP commented on October 16, 2024
Still Preparing Hopefully these are helpful
UNITED STATES
upvote

dado commented on October 16, 2024
cool thanks
BELGIUM
upvote

Harry commented on October 16, 2024
Thanks for the sample exam!
UNITED STATES
upvote