You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654.
What is this project's schedule variance?

  1. -$48,654
  2. 13 percent
  3. -$225,000
  4. 0.98

Answer(s): C

Explanation:

he schedule variance can be found by subtracting the planned value form the earned value. In this instance, it is $2,025,000 minus $2,250,000. SV = 2,025,000 - 2,250,000 = -225,000 Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target.
Answer option A is incorrect. This is the cost variance for the project.
Answer option B is incorrect. 13 percent is not a valid answer.
Answer option D is incorrect. This is not a valid variance for this question; variances are typically negative numbers.



The figure given below demonstrates the communication model for a project.
What role does the component E play in the communications model?

  1. Static
  2. Deterrent
  3. Noise
  4. Barrier

Answer(s): C

Explanation:

Noise is anything that disrupts the communication method such as static on the telephone line, distracting conversations, or misunderstandings.
Answer option A is incorrect. Static is an example of noise, but it is not part of the communication model.
Answer option D is incorrect. A barrier to communication is when communication cannot happen under the present conditions.
Answer option B is incorrect. A deterrent is not a valid part of the communication model.



Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

  1. Scope of statement
  2. Project charter
  3. Statement of work (SOW)
  4. WBS

Answer(s): C

Explanation:

A statement of work (SOW) is a document that captures and defines the work activities, deliverables and timeline that a vendor will execute against in performance of work for a customer. Detailed requirements and pricing are usually specified in it, along with many other terms and conditions. SOW is a narrative description of products or services to be supplied by the project. For internal projects, the project initiator or sponsor provides the statement of work based on business needs, product, or service requirements. For external projects, the statement of work can be received from the customer as part of a bid document.
Answer option A is incorrect. Scope of statement gives the narrative description of the project scope.
Answer option B is incorrect. Project charter is a document that formally authorizes a project manager to work on a project.
Answer option D is incorrect. WBS is a tool that defines a project and groups the project discrete work in a way that helps organize and define the total work scope.



Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned.
What is the cost variance for this project that Fred needs to report to management?

  1. $122,845
  2. -$51,000
  3. -$85,000
  4. Zero

Answer(s): B

Explanation:

The cost variance for the project is -$51,000. You can find the cost variance by using the formula earned value minus planned value. In this instance, it is: CV = EV - AC = (0.60* 2,456,900) - 1,525,140 = -51,000
Answer option C is incorrect. -$85,000 is the project's variance at completion.
Answer option A is incorrect. $122,845 is the project's schedule variance.
Answer option D is incorrect. There is a cost variance on this project of -$51,000.



Page 14 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Mogolo commented on September 18, 2024
good questions and answers
BOTSWANA
upvote

lekshmi commented on September 18, 2024
Thank you for providing these very helpful dumps.
AUSTRALIA
upvote

Mazin commented on September 18, 2024
Is this still valid? I am having the exam on 21 Sept.
JORDAN
upvote

Prameela commented on September 18, 2024
Good Questions
Anonymous
upvote

doctor kekana commented on September 18, 2024
hope to pass
Anonymous
upvote

Troy commented on September 18, 2024
I purchased the full version. From what I have seen so far these are similar questions I saw in my exam which I failed last week. I contacted this site and they got me this exam dump. Very grateful.
UNITED STATES
upvote

Paras Gupta commented on September 17, 2024
great it a good course
Anonymous
upvote

Kgalaletso commented on September 17, 2024
This is a beautiful tool thank you for making ot available
BOTSWANA
upvote

Kapoor commented on September 17, 2024
Even though some answers are not 100% complete the questions are from real exam. It pretty much help me pass. But I had to buy the full version in PDF.
Anonymous
upvote

Jayeer commented on September 17, 2024
I must tell you that you are not going to be able to pass this exam without using dumps. It is unreasonable hard and complicated.
Spain
upvote

Sadie commented on September 16, 2024
These are helpful
Anonymous
upvote

Maresh commented on September 16, 2024
Does anyone clear the exam P_SAPEA_2023 with these dumps? Please confirm.
Anonymous
upvote

John Helper commented on September 16, 2024
Good collection, will definitely help
Anonymous
upvote

MRS Resa commented on September 16, 2024
Gud It is very useful
Anonymous
upvote

CoolGuy commented on September 16, 2024
Came out as a winner. I bought the full version and managed to pass the exam.
Anonymous
upvote

Sulaksha commented on September 16, 2024
Good site to practice
Anonymous
upvote

Guy Folke commented on September 16, 2024
Excellent prep material
Anonymous
upvote

Gelard commented on September 16, 2024
This dump PDF gets the job done. Good service and good quality content. Found a couple of wrong answers but over helped me pass.
UNITED KINGDOM
upvote

Amy commented on September 15, 2024
Great learning
Anonymous
upvote

Tedt commented on September 15, 2024
Great learning
Anonymous
upvote

Test commented on September 15, 2024
GreT learning
Anonymous
upvote

Test commented on September 15, 2024
Great learning
Anonymous
upvote

Test commented on September 15, 2024
Good question
Anonymous
upvote

Sandro commented on September 15, 2024
this is a beautiful tool. passed after a week of studying
Anonymous
upvote

Anonymous commented on September 15, 2024
Someone left a comment stating that this guide is not free. I'd say using this digital format, not the PDF document, is free. I'd also add, with all due respect, that no one should expect to receive a freebie study guide in the mail without a price, and that is because such documents do cost the producers some money.
UNITED STATES
upvote

Anonymous commented on September 14, 2024
Impressive, satisfactory, and comprehensive material that lives up to pars and a little more. Thanks for producing it and making it available to us.
UNITED STATES
upvote

Sohrab commented on September 14, 2024
Hello everyone, My name is Sohrab and I am preparing for this exam. If you guys have any tips to share it would be wonderful and a great help.
Anonymous
upvote

Yorika commented on September 14, 2024
Quite impressive and accurate. The full version is well worth it with the Buy 1 Get one free deal. Basically you get 2 exams with 50% discount.
UNITED STATES
upvote

Sunny commented on September 14, 2024
I am pleased to let you know that I passed this exam last Friday. Here are some feedback to share: 1- The exam is tough so you must read and read and prepare 2- They give you enough time. Skip the questions you don't know and come back to it at the end. 3- Use this exam dumps. I saw most these questions in the exam. Good luck.
UNITED STATES
upvote

Gilbert commented on September 14, 2024
Cant wait to pass mine
Anonymous
upvote

Morgan commented on September 14, 2024
Just passed this exam. It was hard and stressful but saw most of these questions in there.
EUROPEAN UNION
upvote

Mombasa commented on September 14, 2024
Can you all f***ing b**ches post some helpful comments here or share your experience?
Anonymous
upvote

Anonymous commented on September 14, 2024
This material is a comprehensive, excellent study guide rather than just a brain dump of prior exams.
UNITED STATES
upvote

Anonymous commented on September 14, 2024
This is a thorough, explanatory, simple, yet detailed set of questions covering CISM's entire spectrum. Thanks for all the efforts.
UNITED STATES
upvote