You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is.
What value do you report?

  1. -$135,000
  2. .67
  3. .81
  4. -$65,000

Answer(s): C

Explanation:

Cost performance index (CPI) is used to calculate performance efficiencies. It is used in trend analysis to predict future performance. CPI is the ratio of earned value to actual cost. The CPI is calculated based on the following formula: CPI = Earned Value (EV) / Actual Cost (AC) If the CPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The CPI value of 1 indicates that the project is right on target. In this instances it is $270,000 divided by $335,000 for a CPI of .81.
Answer option B is incorrect. .67 is actually the schedule performance index.
Answer option D is incorrect. -$65,000 is the cost variance for the project.
Answer option A is incorrect. -$135,000 is the schedule variance of the project.



Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

  1. -$75,000
  2. -$42,000
  3. -$45,000
  4. -$65,000

Answer(s): A

Explanation:

The schedule variance is found by subtracting the planned value from the earned value. The earned value is the percentage of the project completeness multiplied by the BAC. Planned value is the percetage of where the project should be at this time multiplied by the BAC. Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. In this example, EV = 40% of BAC = 300,000, and PV = 50% of BAC = 375,000 SV = 300,000 - 375,000 = -75,000 Answer options C, B, and D are incorrect. These are not the correct values for the schedule variance.



You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

  1. $142,000
  2. $232,000
  3. $41,750
  4. $23,750

Answer(s): D

Explanation:

Contingency reserves are estimated costs to be used at the discretion of the project manager to deal with anticipated, but not certain, events. These events are "known unknowns" and are part of the project scope and cost baselines. The contingency reserve is calculated by multiplying the probability and the impact for the risk event value for each risk event. The sum of the risk events equals the contingency reserve for the project. Note that Risk D is a positive risk amount.
Answer option C is incorrect. This value is the sum of the risk events if you did not include Risk D as a positive risk value.
Answer option A is incorrect. This is a sum of the risk event.
Answer option B is incorrect. This is a sum of the risk events without including Risk D as a positive risk event.



Mary is the project manager for her company. She's working with the project team to compress the project schedule as the project must be completed by December 30. For some of the project activities, she and the project team have agreed to crash the project work.
What must be true of these project activities for crashing to be acceptable?

  1. The activities must be of fixed duration.
  2. The activities must be effort-drive.
  3. The activities must not be susceptible to the Law of Diminishing Returns.
  4. The activities must be risk-free.

Answer(s): B

Explanation:

Crashing is the addition of project resources to complete effort-driven activities in faster time. By adding more labor the activity can be completed faster.
Crashing is a schedule compression technique to obtain the greatest amount of compression for the least incremental cost. Crashing works
for activities where additional resources will shorten the duration. Approving overtime, bringing in additional resources, paying to expedite
delivery to activities on the critical path are examples of crashing.
Answer option A is incorrect. An activity of fixed duration, such as printing 100,000 brochures in a printing press, won't be completed faster by
adding more effort.

Answer option D is incorrect. Activities need not be risk-free to use project crashing.
Answer option C is incorrect. All effort-driven activities are susceptible to the Law of Diminishing Returns. By adding more labor the value of
the yield of the work decreases because of the cost of the labor added to the project work.



Page 22 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Mohammad commented on September 25, 2024
helpful, but i think it should be updated
Anonymous
upvote

Harish commented on September 25, 2024
Good level of questions
Anonymous
upvote

Kiran commented on September 25, 2024
Good collection
Anonymous
upvote

seb Tan commented on September 25, 2024
Very accurate and curated
AUSTRALIA
upvote

Mario commented on September 25, 2024
Passed my automation anywhere ADVANCED - RPA- PROFESSIONAL exam. Thank you website owner.
Italy
upvote

Oluwal commented on September 24, 2024
Great questions
UNITED STATES
upvote

Tanu commented on September 24, 2024
Great study material to prepare for the exam
Anonymous
upvote

Mohammed commented on September 24, 2024
Thank you for providing this exam dumps. The site is amazing and very clean. Please keep it this way and don't add any annoying ads or recaptcha validation like other sites.
GERMANY
upvote

Pranesh commented on September 24, 2024
preparing for the exam. little help might be good
UNITED STATES
upvote

hriosm commented on September 24, 2024
must be 10, five vms with private and public ip...one per interface.
MEXICO
upvote

Tim commented on September 24, 2024
I recently used this site for my certification prep, and I’m thrilled with the outcome! The exam dumps were thorough and mirrored the actual exam content perfectly. I felt confident and well-prepared, ultimately passing with ease! I highly recommend this site to anyone aiming to succeed in their certification exams!
UNITED STATES
upvote

Kumar commented on September 24, 2024
Good news and bad news. Good news is the questions are valid. Bad news is that you need to buy the full PDF version. But with 50% discount when you buy 2 or more exams is not bad.
INDIA
upvote

Joachim commented on September 24, 2024
While free AZ-900 exam braindumps might seem tempting, they often come with risks like outdated information or inaccuracies. Investing in reliable study materials, like those from this site ensures you get the latest and most accurate content to help you succeed.
UNITED STATES
upvote

Wally commented on September 24, 2024
This certification exam is freaking hard. Either you must be a genius to pass or use these exam dumps.
Anonymous
upvote

Idris Abraham Idilli commented on September 23, 2024
Very interesting
Anonymous
upvote

Debaj commented on September 23, 2024
are these useful in september 2024 exam?
OMAN
upvote

Venkatesh Aiyar commented on September 23, 2024
I will be taking this exam in early December. If anyone has taken or passed this exam recently, please let me know what I should focus on other than the usual suspects such as consolidation, cash flow etc.
UNITED STATES
upvote

Suhas commented on September 23, 2024
its helpful
UNITED STATES
upvote

Surendar G commented on September 23, 2024
I Need Outsystems Dumps Questions and answers
UNITED STATES
upvote

Suhas commented on September 23, 2024
very helpful
INDIA
upvote

Venkat commented on September 23, 2024
I am preparing for exam. It looks nice material
UNITED STATES
upvote

Paul commented on September 22, 2024
Nice one . Good to know
CANADA
upvote

Kyle commented on September 22, 2024
Get the PDF full version. It is well worth the prices. I used the discount code: 50%OFF Ask them for the discount code and they wi6swnd it to you.
Canada
upvote

Alicia commented on September 22, 2024
question 152-the correct answer is B, not C
Anonymous
upvote

meep commented on September 22, 2024
meep meepmeep meepmeep meepmeep meepmeep meep
UNITED KINGDOM
upvote

Solomon commented on September 22, 2024
I have SAA-C03 exam this coming saturday. Are the dumps here still valid?
Anonymous
upvote

Sunil commented on September 22, 2024
Good for exam practice
Anonymous
upvote

Abu commented on September 22, 2024
I did not know these questions were available online. I did not believe and trust them and studied quite a lot and just used these questions for practice. But most of the questions turned out to be in the exam.
UNITED STATES
upvote

abhijeet commented on September 22, 2024
preparing for exam
Anonymous
upvote

Nermenda commented on September 22, 2024
The exam was brutally hard but thanks to these questions bank. Most of the questions were in the exam.
INDIA
upvote

Md Nur Hosen commented on September 21, 2024
Preparing for exam
Anonymous
upvote

Takki commented on September 21, 2024
I used the exam dumps to pass my test, and now my brain's convinced it's a genius. Thanks to this dumps—I promise I studied... kinda.
Singapore
upvote

Last-Minute Miracles commented on September 21, 2024
Thanks to this exam dumps and for posting it free.
Anonymous
upvote

Jodah commented on September 21, 2024
I don’t always study, but when I do, I use exam dumps. Now I’m certified.
UNITED KINGDOM
upvote