Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic.
What is soft logic?

  1. Soft logic describes activities that do not have particular resources assigned to them.
  2. Soft logic describes activities that can be completed in any order.
  3. Soft logic describes activities that can have lead time added to them.
  4. Soft logic describes activities that can be crashed because they are effort-driven.

Answer(s): B

Explanation:

Soft logic can be completed in any order without affecting the outcome of the deliverables. Soft logic is also known as preferential logic, preferred logic, and discretionary dependency. It is defined on the basis of knowledge of best practices and standard procedures for the particular application area. Soft logic is defined by the project management team based on well- known practices in a specific desired sequence.
Answer options A, D, and C are incorrect. These are not valid definitions of soft logic.



Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes?

  1. Scope Verification
  2. Configuration Management System
  3. Project Management Information System
  4. Integrated Change Control

Answer(s): B

Explanation:

The change management system comprises several components that guide the change request through the process.
When a change request is made, it will affect the project scope. The Configuration Management System evaluates the change request, and documents the features and functions of the change on the project scope.
What is Configuration Management System?
Configuration Management System is a subsystem of the overall project management system. It is a collection of formal documented procedures used to identify and document the functional and physical characteristics of a product, result, service, or component of the project. It also controls any changes to such characteristics, and records and reports each change and its implementation status. It includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling changes. Audits are performed as part of configuration management to determine
if the requirements have been met.
Answer option D is incorrect. Integrated Change Control, part of the change control system, does not document changes to the features and functions of the project scope. It evaluates the change's impact on eight knowledge areas: scope, time, cost, quality, human resources, communication, risk, and procurement.
What is Perform Integrated Change Control?
Perform Integrated Change Control is the process of reviewing all change requests, approving changes, and controlling changes to the deliverables and organizational process assets in a project. Perform Integrated Change Control has to do with influencing the things that cause change, determining that the change is required or has happened, and managing the change.
Answer option A is incorrect. Verify scope is a process of formalizing acceptance of the completed project deliverables. It is an inspection- driven process the stakeholders will complete to inspect the project scope deliverables. It is typically performed at the end of the phase and at the end of the project.
Answer option C is incorrect. The Project Management Information System (PMIS) is an information system consisting of the tools and techniques used to gather, integrate, and disseminate the outputs of project management processes. It is used to support all aspects of the project from initiating through closing, and can include both manual and automated systems. It is the parent of the change control process. It is a system that includes all of the change control processes for scope, time, cost, and procurement. Configuration management is part of the PMIS.



You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, the project sponsor, and ten members of your project team.
What type of communication method are you using in this instance?

  1. Interactive communication
  2. Active communication
  3. Pull technique
  4. Push technique

Answer(s): A

Explanation:

Any meetings, phone calls with multiple participants, or conferences are examples of the interactive communications.

Answer option B is incorrect. Active communication is not a PMBOK term for project management.
Answer option D is incorrect. A push technique describes a distribution from the project manager out to the message recipients, such as email.

Answer option C is incorrect. A pull technique describes a distribution method where the recipients of the message pull the message from a
source, such as a Web server.



Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date.
What is Holly's schedule performance index for this project?

  1. 1.07
  2. 0.98
  3. 0.89
  4. Ten percent

Answer(s): C

Explanation:

The schedule performance index is found by dividing the earned value by the planned value. For Holly's project, it would be as follows:
SPI = EV/PV
= (0.85*9,850,400)/(0.95*9,850,400)
=8,372,840/9,357,880
=0.89
Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance.
SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula:
SPI = Earned Value (EV) / Planned Value (PV)
If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.
Answer option D is incorrect. Ten percent is not a valid calculation for this question.
Answer option B is incorrect. 0.98 is the cost performance index.
Answer option A is incorrect. 1.07 is the to-complete performance index based on the BAC.



Page 25 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Srikanth commented on October 20, 2024
Useful to prepare for the exam
Anonymous
upvote

Alex commented on October 20, 2024
This exam is super duper hard. So prepare for it guys. I only passed it because of these questions. God bless the owner of this site.
UNITED STATES
upvote

Petrious commented on October 20, 2024
The site provides good content and very reliable support team. Very quick to reply to questions.
GERMANY
upvote

Rashmi commented on October 20, 2024
Good Content
Anonymous
upvote

Manish commented on October 19, 2024
Hi it's a good initiative
Anonymous
upvote

Veronica commented on October 19, 2024
Brain dump questions are new to me...I'm not sure how to respond to this since I only answered a handful of questions
UNITED STATES
upvote

Kamran commented on October 19, 2024
Useful resource
UNITED STATES
upvote

AC commented on October 19, 2024
For a moment no, comment, still moving well
Anonymous
upvote

johnny commented on October 19, 2024
great insight
Anonymous
upvote

Marc commented on October 18, 2024
What the best way to learn terraform?
UNITED STATES
upvote

murad commented on October 18, 2024
Very helpful for certs
JORDAN
upvote

Jack commented on October 18, 2024
are these legit ?
Anonymous
upvote

Juan commented on October 18, 2024
From until what page number is enough to pass the certification?
Anonymous
upvote

Sandeep commented on October 18, 2024
This is very helpful for exam crack
UNITED STATES
upvote

Cheron commented on October 18, 2024
Before all i thank to you for your support. I passed my 2 exams I purchased with full version. I got 90% in one exam and in 2 exam I got 86%.
Anonymous
upvote

LA commented on October 18, 2024
Hi there, I have scheduled my EXAM and will share my experience if these questions are valid or not.
Anonymous
upvote

Mazin commented on October 18, 2024
Good questions
Anonymous
upvote

Test commented on October 18, 2024
Test are these teak answeres?
Anonymous
upvote

anonymous commented on October 17, 2024
can someone tell me if this is real questions
UNITED STATES
upvote

Steven commented on October 17, 2024
Questions are spot on and I passed the exam.
UNITED STATES
upvote

Ntombi commented on October 17, 2024
i find the questions helpful for my exam preparation
Anonymous
upvote

Ntombi commented on October 17, 2024
The questions help me to see if I understood what I have learned
Anonymous
upvote

ntombi commented on October 17, 2024
writing exam at the end of the month
Anonymous
upvote

Apvj commented on October 17, 2024
Need to update section 5 questions,it was all new question today in exam , unitl section 4 it was fine even though pattern of question changed
Anonymous
upvote

ghada commented on October 17, 2024
it helps a lot
Anonymous
upvote

John commented on October 17, 2024
Good mock exam
Anonymous
upvote

test commented on October 17, 2024
Good content
UNITED STATES
upvote

Manoo commented on October 17, 2024
Hello guys, I hope everyone is doing good and preparing for this exam. I just wanted to share my experience about my exam. I wrote this exam yesterday and I passed. The key is to focus on each topic and memorize all these questions. You see most of them in your test. Good luck
INDIA
upvote

Ad commented on October 17, 2024
Hi I am new to IT
Anonymous
upvote

sadai commented on October 17, 2024
I really apricate this helpful test thank you so much
Anonymous
upvote

Lee commented on October 17, 2024
This is a very good resource. I'm glad this is provided for free for everyone to pass their exam. I'm sure everyone knows how difficult these exams are.
UNITED STATES
upvote

BANKEY BIHARI LAL commented on October 17, 2024
Very good mock exams as per the actual exam standards.
INDIA
upvote

Faruk commented on October 17, 2024
is free content is enough for pas az-900 ?
Anonymous
upvote

chad johnson commented on October 16, 2024
learning from this test
UNITED STATES
upvote