George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule.
What value should George report in this instance?

  1. .96
  2. -$77,800
  3. $-34,500
  4. -$13,800

Answer(s): B

Explanation:

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. The earned value in this instance is forty percent of the project budget, $778,000, and the planned value is $398,000 because George is to be fifty percent done at the end of the second quarter, as the work is spread evenly across all quarters. The schedule variance is -$77,800 for the project.
Answer option A is incorrect. .96 represents the cost performance index.
Answer option C is incorrect. -$34,500 represents the project's variance at completion if the project continues as is.
Answer option D is incorrect. -$13,800 is the cost variance for the project.



You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95.
What does this term mean?

  1. It means the largest schedule variance you can have is five percent.
  2. It is the earned value divided by the planned value for your project.
  3. It is the expectation of management to be 95 on schedule at 95 percent of the project.
  4. It means you will need to earn at least 95 cents per dollar invested in the project.

Answer(s): A

Explanation:

Conformance to schedule is a required adherence for the project's schedule. In this instance, the project manager must not allow the schedule to slip more than five percent.
Answer option B is incorrect. This is the description of the schedule performance index.
Answer option D is incorrect. This is the description of the cost performance index.
Answer option C is incorrect. This is not a valid statement about the project performance.



Which one of the following estimate types is a form of expert judgment?

  1. Parametric estimate
  2. Analogous estimate
  3. Bottom-up estimate
  4. Definitive estimate

Answer(s): B

Explanation:

An analogous estimate is a form of expert judgment because it relies on historical information. The historical information, assuming that it is accurate, serves as the conduit to the expert that created the historical information.
Answer option C is incorrect. A bottom-up estimate creates an activity duration estimate for each work package in the WBS.
Answer option A is incorrect. Parametric estimating uses a parameter, such as 10 hours per fixture installation, as a base to predict the duration of the project.
Answer option D is incorrect. A definitive estimate, also known as a bottom- up estimate, accounts for the cost of each work package.



You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date.
What is your schedule performance index for this project?

  1. 80
  2. 1.02
  3. 102
  4. 0.80

Answer(s): D

Explanation:

The schedule performance index can be found by dividing the earned value by the planned value. In this project, it's $447,000 divided by the $558,750 for a value of 0.80. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula:

SPI = Earned Value (EV) / Planned Value (PV)
If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.

Answer option A is incorrect. "80" is not the same value as ".80".
Answer option B is incorrect. 1.02 is the cost performance index.
Answer option C is incorrect. 102 is not a valid calculation for this question.



Page 3 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Tanuja Bhusal commented on December 26, 2024
Good Questions
Anonymous
upvote

anonymous commented on December 26, 2024
Just going through the questions for my understanding of Power Bi
UNITED STATES
upvote

laks commented on December 26, 2024
so far seems good
UNITED STATES
upvote

Mooni commented on December 26, 2024
It's really good
SAUDI ARABIA
upvote

Phoebe commented on December 26, 2024
Good questions
FRANCE
upvote

rz commented on December 26, 2024
It's very helpful for exam
TAIWAN PROVINCE OF CHINA
upvote

Nitesh Kumar Singh commented on December 26, 2024
Nice to attend
Anonymous
upvote

Pankaj Kumar commented on December 26, 2024
Its good to have all the relevant questions here.. Thanks for help!
UNITED STATES
upvote

ian commented on December 26, 2024
yes, is this still valid?
UNITED STATES
upvote

Onkar commented on December 26, 2024
Questions looks promising.
Anonymous
upvote

JcD commented on December 25, 2024
Great learning
Anonymous
upvote

Sam commented on December 25, 2024
Are these real questions? They seem too easy to be true
UNITED STATES
upvote

Netra commented on December 25, 2024
Very useful
UNITED STATES
upvote

Prg commented on December 25, 2024
good set of questions
Anonymous
upvote

n commented on December 25, 2024
Question are
Anonymous
upvote

Ni commented on December 25, 2024
useful questions
Anonymous
upvote

ry commented on December 24, 2024
very helpful
Anonymous
upvote

Jatin Gohil commented on December 24, 2024
Good contents. The exams questions are real
Anonymous
upvote

Anonymous commented on December 24, 2024
very useful
CHILE
upvote

Mohamedk commented on December 24, 2024
It's very nice
Anonymous
upvote

Amer commented on December 24, 2024
Thanks alot
EGYPT
upvote

shankar commented on December 24, 2024
good set of questions
CHINA
upvote

VARSHA commented on December 24, 2024
GOOD QUSTIOENS.. LIKED IT
Anonymous
upvote

Robin commented on December 24, 2024
nice course
Anonymous
upvote

Rama laksmana commented on December 23, 2024
Good question
UNITED STATES
upvote

Chandru commented on December 23, 2024
Nice questions
UNITED STATES
upvote

Amr commented on December 23, 2024
Good tutorial
Anonymous
upvote

hari commented on December 23, 2024
Preparing for exam
INDIA
upvote

Ichigo Kurosaki commented on December 23, 2024
Can I pass the exam, if I have done suppose 150 questions from here?
MALAYSIA
upvote

Emma commented on December 23, 2024
Really helpful for preparing the exam
FRANCE
upvote

Siva commented on December 23, 2024
Good ones with the quick start
INDIA
upvote

sj commented on December 22, 2024
good set of questions
Anonymous
upvote

sj commented on December 22, 2024
Questions that are typically not covered as part of the aws learning course videos
Anonymous
upvote

sowmya commented on December 22, 2024
helpfull to prepare for the exam
Anonymous
upvote