Free PMI-SP Exam Braindumps (page: 6)

Page 6 of 82

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:



You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G . How much float is available for Activity G to help offset the risk event?

  1. Five days
  2. Four days
  3. Eleven days
  4. Zero

Answer(s): D

Explanation:

There is no float available for Activity G because it is on the critical path. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, A, and C are incorrect. There is no float available for Activity G because it is on the critical path.



Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?

  1. Imminent activity management
  2. Rolling wave planning
  3. Predecessor-only diagramming
  4. Decomposition

Answer(s): B

Explanation:

Rolling wave planning is a technique to plan and do the most imminent project work before moving onto the details that are far off in the project schedule and project plan. Rolling wave planning is a technique for performing progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure. The work to be performed within another one or two reporting periods in the near future is planned in detail as work is being completed during the current period.
Answer option D is incorrect. Decomposition is the process of breaking down work packages into the activity list. Answer options A and C are incorrect. These are not valid project management terms.



Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?

  1. Scope baseline
  2. Organizational process assets
  3. WBS
  4. Enterprise environmental factors

Answer(s): C

Explanation:

According to the PMBOK, Gina will not need the WBS directly, but will rely on the scope baseline.A Work Breakdown Structure (WBS) in project management is a tool that defines a project and groups the project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option A is incorrect. The scope baseline is an input to define the project activities.
Answer option D is incorrect. Enterprise environmental factors are an input to define the project activities.
Answer option B is incorrect. Organizational process assets are an input to define the project activities.



You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float.
What is the difference between total float and free float?

  1. Total float is the amount of time an activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.
  2. Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project successors.
  3. Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project predecessors.
  4. Total float is the amount of time a non-critical activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

Answer(s): B

Explanation:

Total float is the time you can delay an activity without delaying the project end date, whereas free float is on each activity and does not affect the early start date of successor activities. Float, also called slack, is the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available: Free Float: It is the amount of time a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Total Float: It is the total amount of time that a schedule activity may be delayed

from its early start date without delaying the project finish date, or violating schedule constraint. Float is calculated by using the critical path method technique. Answer options C, A, and D are incorrect. These are not accurate definitions of free float and total float.



Page 6 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

nahdus commented on November 29, 2024
all comments are original?
Anonymous
upvote

Sanjay Dinda commented on November 29, 2024
So far all good
UNITED KINGDOM
upvote

Naveen Ahlam commented on November 29, 2024
Great stuff
Anonymous
upvote

nancy commented on November 29, 2024
Very helpful
Anonymous
upvote

M commented on November 29, 2024
Is this still valid ?
SLOVAKIA (Slovak Republic)
upvote

Mira commented on November 29, 2024
Great tool and questions!
Anonymous
upvote

Joaquin commented on November 29, 2024
These are good questions.
Anonymous
upvote

Joaquin commented on November 29, 2024
Good questions.
Anonymous
upvote

naveen naveen commented on November 29, 2024
Very useful
Anonymous
upvote

Kadeer commented on November 29, 2024
Very professional support. I sent an email about the full version of this exam I purchased and they replied within 5 minutes and setup everything for me. I ended up passing my exam with this dump. I highly recommend.
Singapore
upvote

hello commented on November 28, 2024
Great collection of the questions covering all aspects
INDONESIA
upvote

Chaminda commented on November 28, 2024
great papers
Anonymous
upvote

mihir commented on November 28, 2024
Valid dumps
INDIA
upvote

AK commented on November 28, 2024
Are these enough?
UNITED STATES
upvote

Nacho commented on November 28, 2024
What a great week. Passed this freaking exam...at last. Now I can enjoy the Thanks Giving. Happy Thanks Giving to all.
UNITED STATES
upvote

Aman commented on November 28, 2024
Passed this exam and got 93%. Valid exam dump.
France
upvote

Traveller69 commented on November 28, 2024
I sat for this exam today. The questions are - I would say around 85% to 90% the same. I got 87% with just 2 weeks of studying from the PDF full version of this exam.
Canada
upvote

AD AD commented on November 28, 2024
thanks for the exact solution
Anonymous
upvote

Lee commented on November 27, 2024
So far so good
UNITED STATES
upvote

Hernandoz commented on November 27, 2024
I am happy to say that I managed to clear this exam. Thanks to this website and great exam content and questions in this dump.
Mexico
upvote

Sakshay commented on November 27, 2024
Not sure if I am the only one who finds this exam super tricky and hard. Looking at these questions I can recall that most of these questions were in the exam. But last time I did not know about these questions so I failed. I think I am going to be okay this time to pass. These questions looks very promising.
INDIA
upvote

Ramparsat commented on November 27, 2024
The full PDF version has way more questions than this free version. I believe if you a good knowledge and understanding of the certification exam then you should be able to pass it using the free version. Otherwise, go with full version and don't take any chance.
Australia
upvote

Fei commented on November 26, 2024
Very good resources
UNITED STATES
upvote

Maruthi commented on November 26, 2024
Good collection of the questions covering all aspects
AUSTRALIA
upvote

Ganapathy commented on November 26, 2024
Cam wr study and pass this Microsoft AZ-900 exam in India
Anonymous
upvote

Maruthi commented on November 26, 2024
Going all good
AUSTRALIA
upvote

Geroge commented on November 26, 2024
Providing this service is much appreciated. This free exam dumps is helping me a lot.
Romania
upvote

Anne commented on November 26, 2024
Took the exam today and I passed. I think I only had one new question, all were from here including the PBQ's
SOUTH AFRICA
upvote

elhassan commented on November 26, 2024
many thanks
Anonymous
upvote

willy commented on November 26, 2024
this web site help me to prepare for my exams
UNITED STATES
upvote

willy commented on November 26, 2024
Much better than the other website. its very helpful
UNITED STATES
upvote

Sigsauer9111 commented on November 26, 2024
I am looking to write the Ms-900, Just want to find out how accurate this exam dump and answers are in relation to the real exam?
Anonymous
upvote

Bright Edet commented on November 26, 2024
Valid dumps
Anonymous
upvote

jijo commented on November 26, 2024
its helpful
INDIA
upvote