Free PMI-SP Exam Braindumps (page: 5)

Page 5 of 82

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98.
What type of report would you create for management, if these instances develop in your project?

  1. Cost variance report
  2. Exceptions report
  3. Performance management report
  4. Schedule variance report

Answer(s): B

Explanation:

The best answer is simply an exception report.

An exception report refers and documents the major mistakes, mishaps, and goofs. In other words, it itemizes the important and critically significant piece of documentation that is vital to the proper and effective functioning of a project. It does not document what has gone right, but rather documents what has gone wrong.
Answer option C is incorrect. A performance management report is not a valid project management report.
Answer option A is incorrect. The question is asked a out cost and schedule so this answer would not be appropriate for both the cost and the schedule.
Answer option D is incorrect. The question is asked about cost and schedule so this answer would not be appropriate for both the cost and the schedule.



You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450.
What is this project's to- complete performance index based on the current BAC?

  1. 1.02
  2. 0.010
  3. 0.75
  4. 0.95

Answer(s): A

Explanation:

This project is not performing well on schedule, but moderately well on costs. The project's TCPI based on the current BAC is 1.02. To-complete Performance Index (TCPI) is the measured projection of the anticipated performance required to achieve either the BAC or the EAC. TCPI indicates the future required cost efficiency needed to achieve a target EAC (Estimate At Complete).Once approved, the EAC supersedes the BAC as the cost performance goal. Any significant difference between TCPI and the CPI needed to meet the EAC should be accounted for by management in their forecast of the final cost. The formula for TCPI is as follows: TCPI = {(BAC- EV)/(BAC-AC)}
Answer option D is incorrect. 0.95 is the project's TCPI value based on the estimate at completion.
Answer option C is incorrect. 0.75 is the project's schedule performance index.
Answer option B is incorrect. 0.010 is not a valid calculation.



Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule.
Which of the following is a tool and technique for the Schedule Development process?

  1. Schedule compression
  2. Reserve analysis
  3. Variance analysis
  4. Expert judgment

Answer(s): A

Explanation:

Schedule compression is a tool used as part of the Schedule Development process. The tools and techniques for schedule development are as follows: Schedule network analysis Critical path method Critical chain method Resource leveling What-if scenario analysis Applying leads and lags Schedule compression Scheduling tool Answer options D, B, and C are incorrect. These are not tools and techniques for schedule development.



You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90.
What time will you record for this activity?

  1. 48
  2. 20o, 45m, 90p
  3. 90
  4. 45

Answer(s): A

Explanation:

This is an example of a three-point estimate. A three-point estimate records the optimistic, most likely, and the pessimistic duration, and then records an average for the predicted duration Three- point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program Evaluation and Review Technique (PERT). PERT charts the following three estimates:

Most likely (TM): The duration of activity based on realistic factors such as resources assigned, interruptions, etc. Optimistic (TO): The activity duration based on the best-case scenario Pessimistic (TP): The activity duration based on the worst-case scenario The expected (TE) activity duration is a weighted average of these three estimates: TE = (TO + 4TM + TP) / 6 Duration estimates based on the above equations (sometimes simple average of the three estimates is also used) provide more accuracy. It can be calculated as follows: TE = ( 20 + 45*4 + 90) / 6 = 290/6 =48 Answer options B, C, and D are incorrect. These are not the valid answers for this question.



Page 5 of 82



Post your Comments and Discuss PMI PMI-SP exam with other Community members:

Veitnam commented on November 03, 2024
Thank you the website owner for making these exam questions available for free. It helped me clear my paper.
Anonymous
upvote

Anonymous commented on November 03, 2024
Can I pass the exams only with these dumps ?
Anonymous
upvote

Bin Mahamood commented on November 03, 2024
terraform { required_providers { aws = { version = ">= 2.7.0" source = "hashicorp/aws" } } }
Anonymous
upvote

Yizzy commented on November 02, 2024
@Patak when did you take the exam?
Anonymous
upvote

Tadele commented on November 02, 2024
Help full to next exam
Anonymous
upvote

Jaqulin commented on November 02, 2024
I appreciate the service and the questions being free. Finally something free in this world.
FRANCE
upvote

numan commented on November 02, 2024
really helping
GERMANY
upvote

Patak commented on November 01, 2024
I got about 70 to 74 questions are from here. So its worth it.
INDIA
upvote

xxx commented on November 01, 2024
I've used this material for exam preps. Many questions comes from this dump.
ESTONIA
upvote

Timens commented on November 01, 2024
Well done and nicely put together. All valid questions in PDF version.
Netherlands
upvote

Debendra commented on November 01, 2024
Passed the exam. The best Diwalli present!!! Thank you team for this braindumps.
INDIA
upvote

Tdk commented on November 01, 2024
Great staff
SOUTH AFRICA
upvote

Tdk commented on November 01, 2024
Good material
SOUTH AFRICA
upvote

Sophy commented on November 01, 2024
These communities along with the questions posted here assisted me a lot for passing my exam CISSP
UNITED STATES
upvote

Pear commented on November 01, 2024
I had a deadline to pass this exam. These questions dumps came to save me. Very easy and quite accurate.
UNITED STATES
upvote

Kiran P commented on November 01, 2024
very helpful ..
INDIA
upvote

Sree commented on October 31, 2024
This is a good practice test for preparation
UNITED STATES
upvote

ambr commented on October 31, 2024
just doing some preparation
Anonymous
upvote

Caml commented on October 31, 2024
Ok at thé moment
Anonymous
upvote

Caml commented on October 31, 2024
I will Say After trying more questions
Anonymous
upvote

George commented on October 31, 2024
Fun way to learn
ROMANIA
upvote

Damian commented on October 31, 2024
Just passed my exam today. I am going to focus on my second exam. Just an FYI, if you are buying the full version they have a buy 1 get one free deal. Just select 2 exams and add them to shopping cart and you get a 50% off your over all total... automatically.
UNITED STATES
upvote

Temitope commented on October 31, 2024
Good questions
EUROPEAN UNION
upvote

Temitope commented on October 31, 2024
Nice and well structured questions
EUROPEAN UNION
upvote

Mr. K commented on October 31, 2024
Valid exam dump. Passed in first try. Keep the good work and keep it free guys.
UNITED STATES
upvote

Fernanda commented on October 30, 2024
This is a very good practice test, I approve my exam
Anonymous
upvote

Gustavo Gonçalves commented on October 30, 2024
A questão 17 está errada a resposta é letra D. Podem corrigir por favor?
BRAZIL
upvote

DA commented on October 30, 2024
Very good and help a lot for practice
INDIA
upvote

Arthur commented on October 30, 2024
I had an awesome experience passing the AZ-104 on my first attempt! Huge thanks to this site for their support and top-notch materials—it was spot on!
UNITED STATES
upvote

George commented on October 30, 2024
Thanks for all the assistance i got the full PDF version. Highly recommended!
UNITED STATES
upvote

Arthur commented on October 30, 2024
If you're preparing for the AZ-104 exam, I highly recommend checking out these questions. They offer great resources and practice questions that can really help you understand the material and boost your confidence. Good luck with your studies!
UNITED STATES
upvote

RM commented on October 30, 2024
Thank you for the dumps
Anonymous
upvote

Dayanidhi M commented on October 29, 2024
good exam dump
Anonymous
upvote

Vulquin commented on October 28, 2024
Hello, I wanted to take the pdf version for az-140 certification and I can't find where to buy it.
Anonymous
upvote