Free PMP Exam Braindumps
Project Management Professional Questions 616–620 (page: 125)

Updated On: 10-Feb-2026

A client mentioned that in the past 2 months, they have not been invoiced for completed work. The client has communicated that they will release the funds for other activities it the invoices are not sent.
What should the project manager do next?

  1. Work with the client and agree on a schedule to provide them with the invoices
  2. Reach out to the billing team and instruct them to issue the invoices immediately
  3. Review the previous billing information and prepare a corrective action plan
  4. Communicate and inform the client to go ahead and release the funds

Answer(s): C



HOTSPOT (Drag and Drop is not supported).
A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late.
Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.
Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck.
Hot Area:

  1. See Explanation section for answer.

Answer(s): A

Explanation:



Midway through the execution of an agile protect there is a shift in the strategic objectives at the organization level to promote digital transformation.
What should the project manager do next?

  1. Schedule a meeting with the team to assess the impact of the change
  2. Escalate to the product owner and cancel the upcoming iterations
  3. Prepare a user story to handle the change and assign it to the next iteration
  4. Update the risk-prioritized backlog with the strategic change

Answer(s): A



DRAG DROP (Drag and Drop is not supported).
Drag the items on left side to the matching term within the correct project approach on the right side.
Select and Place:

  1. See Explanation section for answer.

Answer(s): A

Explanation:



A project manager is assigned to a project that will improve the business operations for a trading firm. The project team has just completed the discovery phase and needs to make a presentation to the business team in 4 weeks to showcase the feasibility of the solution.
How should the project manager advise the team to proceed?

  1. Develop a conceptual framework.
  2. Develop a request for proposal (RFP).
  3. Develop a prototype.
  4. Develop a minimum viable product (MVP).

Answer(s): C



Viewing page 125 of 285
Viewing questions 621 - 625 out of 2195 questions


Post your Comments and Discuss PMI PMP exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!