A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change in project scope.
How should the project manager respond to this requirement?

  1. Perform an analysis to assess the Impact on the project.
  2. Proceed with the existing company governance policy.
  3. Escalate the issue to upper management and let them decide.
  4. Directly comply with the financial regulations.

Answer(s): A



A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs.
How should the project manager ensure the work continues smoothly?

  1. Postpone the required work on the project until school holidays begin
  2. Continue the work as planned and inform the school when the project team arrives on-site
  3. Advise the school to close for the duration of the project work
  4. Liaise with the school to include nonworking project hours during school start and finish times

Answer(s): D



It is late at night on a weekend when a team member calls the project manager on the telephone. The team member is crying about the pressures of an upcoming deadline.
What should the project manager do?

  1. Review the organization's human resources (HR) policy.
  2. Empathize with the team member and discuss next steps.
  3. Ask the team member to send their concerns in writing.
  4. Schedule a meeting with the team member for the next work day.

Answer(s): B



A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.
In order to help the team, what should the project leader do?

  1. Recommend that the team reviews the length of the iteration with the stakeholders.
  2. Recommend that the product owner reviews the backlog refinement processes.
  3. Recommend limiting the work in progress to improve the team's focus.
  4. Recommend a review of the team members' individual performances.

Answer(s): B