Free RMP Exam Braindumps
PMI Risk Management Professional Exam Questions 96–100 (page: 21)

Updated On: 10-Feb-2026

You are the project manager of the GHQ project for your company. You are working with your project team to prepare for the qualitative risk analysis process. Mary, a project team member, does not understand why you need to complete qualitative risks analysis. You explain to Mary that qualitative risks analysis helps you determine which risks needs additional analysis. There are also some other benefits that qualitative risks analysis can do for the project. Which one of the following is NOT an accomplishment of the qualitative risk analysis process?

  1. Corresponding impact on project objectives
  2. Time frame for a risk response
  3. Prioritization of identified risk events based on probability and impact
  4. Cost of the risk impact if the risk event occurs

Answer(s): D



When does the Identify Risks process take place in a project?

  1. At the Planning stage.
  2. Throughout the project life-cycle.
  3. At the Initiating stage.
  4. At the Executing stage.

Answer(s): B



Sam is the project manager of a construction project in south Florida. This area of the United States is prone to hurricanes during certain parts of the year. As part of the project plan Sam and the project team acknowledge the possibility of hurricanes and the damage the hurricane could have on the project's deliverables, the schedule of the project, and the overall cost of the project. Once Sam and the project stakeholders acknowledge the risk of the hurricane they go on planning the project as if the risk is not likely to happen. What type of risk response is Sam using?

  1. Active acceptance
  2. Passive acceptance
  3. Avoidance
  4. Mitigation

Answer(s): B



You are the project manager of a large project that will last four years. In this project, you would like to model the risk based on its distribution, impact, and other factors. There are three modeling techniques that a project manager can use to include both event-oriented and project-oriented analysis. Which modeling technique does NOT provide event-oriented and project-oriented analysis for identified risks?

  1. Sensitivity analysis
  2. Jo-Hari Window
  3. Expected monetary value
  4. Modeling and simulation

Answer(s): B



You are the project manager of the GHY project for your company. This project has a budget of $543,000 and is expected to last 18 months. In this project, you have identified several risk events and created risk response plans. In what project management process group will you implement risk response plans?

  1. Executing
  2. Planning
  3. Monitoring and Controlling
  4. In any process group where the risk event resides

Answer(s): C



Viewing page 21 of 90
Viewing questions 101 - 105 out of 273 questions