You work as a project manager for TechSoft Inc. You, the project team, and the key project stakeholders have completed a round of quantitative risk analysis. You now need to update the risk register with your findings so that you can communicate the risk results to the project stakeholders - including management. You will need to update all of the following information except for which one?
- Probabilistic analysis of the project
- Probability of achieving cost and time objectives
- Risk distributions within the project schedule
- Trends in quantitative risk analysis