You are the project manager of the NJJ project. Your enterprise environmental factors require that you establish certain risk management rules regarding low risks within your project. What is the best policy for risks with low probability and low impact in the project management?

  1. These risks should be accepted.
  2. These risks should be placed on a watchlist for future monitoring.
  3. These risks should be identified, but dismissed.
  4. These risks should be placed in the risk register.

Answer(s): B



Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?

  1. Acceptance
  2. Transference
  3. Mitigation
  4. Avoidance

Answer(s): B



Fred is the project manager of a large project in his organization. Fred needs to begin planning the risk management plan with the project team and key stakeholders. Which plan risk management process tool and technique should Fred use to plan risk management?

  1. Variance and trend analysis
  2. Information gathering techniques
  3. Planning meetings and analysis
  4. Data gathering and representation techniques

Answer(s): C



Joan is the project manager of the BTT project for her company. She has worked with her project to create risk responses for both positive and negative risk events within the project. As a result of this process Joan needs to update the project document updates. She has updated the assumptions log as a result of the findings and risk responses, but what other documentation will need to be updated as an output of risk response planning?

  1. Scope statement
  2. Lessons learned
  3. Risk Breakdown Structure
  4. Technical documentation

Answer(s): D



You work as a project manager for BlueWell Inc. You with your team are using a method or a (technical) process that conceives the risks even if all theoretically possible safety measures would be applied. One of your team member wants to know that what is a residual risk. What will you reply to your team member?

  1. It is a risk that can not be addressed by a risk response.
  2. It is a risk that will remain no matter what type of risk response is offered.
  3. It is a risk that remains because no risk response is taken.
  4. It is a risk that remains after planned risk responses are taken.

Answer(s): D