Which is NOT a purpose of a Benefits Review Plan?

  1. Define the period over which the cost-benefit analysis will be based
  2. Describe how to measure the performance of the project's products in operational use
  3. Define the scope, timing and ownership of the benefit reviews required
  4. Describe how to measure and confirm any benefits that are to be realised after the project is closed

Answer(s): A

Explanation:

This answer remains the same as question 3. The Benefits Review Plan's purpose does not typically include defining the period for the cost-benefit analysis. Instead, it focuses on outlining how the benefits of the project are to be reviewed and measured after the project's closure.


Reference:

PRINCE2® Foundation official guide and study material. These answers are derived from the official PRINCE2® documentation and study materials available for the PRINCE2® Foundation certification.



What is an off-specification?

  1. A new requirement
  2. A quality tolerance
  3. A type of issue
  4. A major risk

Answer(s): C

Explanation:

An off-specification in PRINCE2 is considered a type of issue that arises when a project deliverable is forecasted to deviate from its agreed-upon specifications or requirements. It is an important part of the issue and change control procedure in PRINCE2, where it's recognized and managed to ensure the project stays aligned with its objectives.


Reference:

PRINCE2 Foundation Training Manual, PRINCE2 official website



Which is a type of issue?

  1. A lesson
  2. A request for change
  3. An Exception Report
  4. A risk with an estimated high impact

Answer(s): B

Explanation:

In the PRINCE2 framework, a type of issue that can commonly occur is a request for change. This refers to a proposal for a change or modification to any aspect of the project, which may involve changes to the project's baseline aspects such as scope, product descriptions, quality criteria, or timeframes.


Reference:

PRINCE2 Foundation Training Manual, PRINCE2 official website



Which is a typical core activity within configuration management?

  1. Quality assurance
  2. Risk management
  3. Verification and audit
  4. Progress reporting

Answer(s): C

Explanation:

Verification and audit is a typical core activity within configuration management according to PRINCE2. This activity involves checking that products meet their requirements and are appropriately approved, and ensuring that all items are correctly accounted for, controlled, and both physically and logically consistent throughout the project lifecycle.