Which of the following would be carried out during the Starting Up a Project process?

  1. Establish the procedure for identifying and managing risks during the project
  2. Create a detailed Business Case
  3. Appoint individuals to carry out the work required in project initiation
  4. Ensure that plans for realizing the post-project benefits are managed and reviewed

Answer(s): C



Which is a purpose of the Starting up a Project process?

  1. Provide the information required for the Project Board to decide whether it is worthwhile initiating the project
  2. Ensure the strategy on how the quality expected by the customer will be achieved
  3. Look for lessons to be learned from this project
  4. Document how changes to products will be captured and reviewed

Answer(s): A



Which of the following is NOT established as part of the pre-project work?

  1. A Plan for the work of initiation
  2. Information on the various ways the project can be delivered
  3. A description of what the project is to deliver
  4. A plan for how and when a measurement of the achievement of the project's benefits can be made

Answer(s): D



Identify the missing word(s) from the following sentence. A project is a [?] that is created for the purpose of delivering one or more business products according to an agreed Business Case

  1. Series of initiatives
  2. Temporary organization
  3. Business as usual activity
  4. Permanent team

Answer(s): B



Please refer to section 1.3 and 'Programme' in the Glossary of the PRINCE2 Manual. (Note that a collection of related projects being directed to deliver outcomes and benefits related to the organization's strategic objectives would be a programme NOT a project)

  1. A temporary team that is created to direct and oversee a collection of related projects in order to deliver outcomes and benefits related to the organization's strategic objectives
  2. A temporary organization that is created for the purpose of delivering one or more business products according to an agreed Business Case
  3. A permanent organization that is created for the purpose of realizing one or more business benefits
  4. A permanent team that is created to deliver a series of business change initiatives

Answer(s): B



Which project characteristic refers to a project involving a team of people working together to introduce a change that will impact others outside the team and sometimes other organizations?

  1. Temporary
  2. Cross-functional
  3. Introduces business change
  4. Uniqueness

Answer(s): B



What characteristic relates to a project having a defined start and defined end?

  1. Uniqueness
  2. Uncertainty
  3. Temporary in nature
  4. Introduces change

Answer(s): C



Which of the following is FALSE regarding PRINCE2 principles?

  1. A project should have a customer/supplier environment
  2. A project should manage by exception
  3. A project should focus on products
  4. A project should be tailored to suit the project environment

Answer(s): A



Viewing page 36 of 92
Viewing questions 281 - 288 out of 724 questions


Post your Comments and Discuss PRINCE2 PRINCE2 Foundation exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!