Which of the following describes the situation when an Issue Report would be produced?

  1. When ever the Project Board instruct the Project Manager
  2. It is only created for those issues that need to be handled formally
  3. Every time someone wishes to bring anything to the attention of the Project Manager
  4. Only if the Project Manager feels it is necessary

Answer(s): B



A pre-requisite of effective issue and change control is the establishment of which of the following?

  1. Use of a change budget and change authority
  2. A risk management procedure
  3. A configuration management system
  4. A Quality Management Strategy

Answer(s): C



Which of the following are typical activities of a configuration management procedure?
1. Impact assessment
2. Control
3. Verification and audit
4. Status accounting

  1. 1, 2, 3
  2. 1, 2, 4
  3. 1, 3, 4
  4. 2, 3, 4

Answer(s): D



Which statement is FALSE regarding a Product Status Account?

  1. A Product Status Account is used as a control document to assist in reviewing progress
  2. A Product Status Account provides information on the state of a product
  3. A Product Status Account is used to inform the Project Manager of what errors were found in a product during a quality review
  4. A Product Status Account is derived from Configuration Item Records

Answer(s): C