Which product produced at project closure would document any unfinished work, ongoing issues and risks?

  1. Project closure notification
  2. Benefits Review Plan
  3. End Project Report
  4. Risk Register

Answer(s): C



Which product would contain information on project and stage tolerance status, products completed during the period and a summary of actual or potential problems and risks?

  1. Product Status Account
  2. Communication Management Strategy
  3. Highlight Report
  4. Risk Register

Answer(s): C



What is a purpose of a Lessons Log?

  1. Document and maintain information on issues
  2. Note who should be sent copies of a Highlight Report
  3. Note information from other projects which could be input to the project's strategies and plans
  4. Document the results of quality checking activities

Answer(s): C



Please refer to A.9 in the PRINCE2 Manual. (A summary of issues and risks would be included but the End Stage Report is not used to 'capture and maintain' information regarding issues and risks.
This would be in the respective Registers.)

  1. Capture and maintain information regarding issues and risks
  2. Document the project's acceptance criteria
  3. Escalate a stage-level tolerance threat to the Project Board
  4. Give a summary of progress to date

Answer(s): D