Free PRINCE2-Foundation Exam Braindumps (page: 37)

Page 36 of 182

Identify the missing word in the following sentence... The purpose of the [ ? ] theme is to define and implement the means by which the project will create and verify products that are fit for purpose.

  1. Plans
  2. Change
  3. Organization
  4. Quality

Answer(s): D



What is the purpose of a change budget?

  1. To correct any errors found in products produced by suppliers
  2. To pay for any increase in scope
  3. To implement risk actions, such as fallback plans
  4. To supplement any cost tolerance being exceeded

Answer(s): B



Which of the following is FALSE regarding the Change theme?

  1. Change control should be used to prevent changes being made to baselined products
  2. Issues can affect the project's performance targets of time, cost, quality, scope, benefits and risk
  3. A pre-requisite of effective issue and change control would be an appropriate configuration management system
  4. Without issue and change control being applied, a project will become unresponsive to its stakeholders

Answer(s): A



Who are allowed to raise an issue?

  1. Only the Project Manager and Team Manager
  2. Anyone with an interest in the project or its outcome
  3. Only the Change Authority
  4. Only members of the project management team

Answer(s): B






Post your Comments and Discuss PRINCE2 PRINCE2-Foundation exam with other Community members:

PRINCE2-Foundation Discussions & Posts