One of the senior managers of the company that is developing the “e-learning course” has worked with ABC Company before. The team manager for the delivery of the “e-learning course” has looked on ABC Company’s intranet, but cannot find any reference to this work. The team manager has contacted the senior manager to discuss this project.
Is this an appropriate application of the “learn from experience” principle, and why?

  1. Yes, because the project involves more than one organization.
  2. Yes, because the team manager should actively look for useful information.
  3. No, because the senior manager should advise the team manager of any lessons.
  4. No, because every project is unique and should deliver specific business objectives

Answer(s): B



When does Directing a Project begin?

  1. From the beginning of Starting up a Project
  2. From the beginning of Initiating a Project
  3. From the completion of Starting up a Project
  4. From the completion of Initiating a Project

Answer(s): C



Which management product do the Project Board use to decide whether to authorize initiation?

  1. Project Brief
  2. Business Case
  3. Project Initiation Documentation
  4. Project Product Description

Answer(s): A



Which of the following is NOT a trigger for the project manager to authorize a work package?

  1. Stage Authorization
  2. Corrective Action
  3. Exception plan approved
  4. Reporting highlights

Answer(s): D



Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

  1. Review the stage status
  2. Review work package status
  3. Report Highlights
  4. Take corrective action

Answer(s): C






Post your Comments and Discuss PRINCE2 PRINCE2 Practitioner exam dumps with other Community members: