Two weeks after starting work the Team Manager noticed that each completed product had exceeded its estimated effort by around 10%. If this trend continues the Work Package will exceed its agreed cost tolerance of 5%. Which 2 actions should the Team Manager take in response to this situation?

  1. Check the status of the products currently being worked on and analyze the effort expended, to determine if the trend is continuing.
  2. Update the Team Plan by increasing all future work estimates by 10%.
  3. Amend the Work Package and ensure that the revised targets are met.
  4. Escalate the situation in the next Checkpoint Report.
  5. Raise an issue that costs will exceed tolerance if the current trend continues.

Answer(s): A,E



The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate people.
Which 2 actions should the Team Manager take to check that the completed products have been approved as required?

  1. Check the Work Package to ascertain who should approve the completed Work Package.
  2. Check the Product Descriptions to ascertain who should have approved the products.
  3. Check the Configuration Management Strategy for product handover procedures.
  4. Check the approval records as required in the Work Package.
  5. Check the Product Descriptions for the quality method required.

Answer(s): B,D



The Work Package has been in progress for four weeks and has four weeks remaining. The Information Technology Team Manager is concerned that he has no idea what the service provider is doing about preparing to accept the transfer of Information Technology equipment and staff. He is uncertain about what should be happening.

Which 2 initial actions should the Team Manager take in response to this concern?

  1. Notify the Project Manager by raising an Exception Report.
  2. Raise this concern in the next fortnightly Checkpoint Report.
  3. Check the Communication Management Strategy to ascertain what records of communications with the service provider are required.
  4. Check the Information Technology Work Package for development interfaces to see whether the service provider Team Manager should have been liaising with the Information Technology team during development.
  5. Raise an issue to notify the Project Manager of this concern.

Answer(s): D,E



Which statement best explains the purpose of Tailor to suit the project environment?

  1. Ensure project controls are based on project's scale, complexity, importance, capability and risk
  2. To use a set of pre-defined templates for the size of project
  3. To tailor the use of the principles to suit the project
  4. To pick which PRINCE2 processes to apply and which to leave out

Answer(s): A



Which of the following principles uses Product Descriptions to provide clarity by defining each product's purpose, composition, derivation, format, quality criteria and quality method?

  1. Tailor to suit the project environment
  2. Focus on products
  3. Manage by stages
  4. Continued business justification

Answer(s): B