Which of the following statements is FALSE regarding the Continued Business Justification?

  1. The justification for the project must remain the same throughout the project
  2. The justification for the project should remain valid
  3. The justification for the project may change
  4. If the project is no longer justified it should be stopped

Answer(s): B



Which of the following principles describes this statement?
"xxx defines tolerances for each project objective to establish limits of delegated authority"

  1. Manage by stages
  2. Focus on products
  3. Manage by exception
  4. Learn from experience

Answer(s): C



Which of the following statements is NOT correct?
The Learn from Experience principle suggests that lessons should be actively sought...

  1. When Starting a Project
  2. When Initiating a Project
  3. As the project progresses
  4. As the project closes

Answer(s): B



View Related Case Study

Which product should show that the photos could be used for other promotional material for the company?

  1. Benefits Review Plan
  2. Lessons Log
  3. Exception Report
  4. End Project Report

Answer(s): D



View Related Case Study

Which product should show that the staff photo sessions were disruptive to the Engineering Department as they had been scheduled during peak work times without consultation with the Engineering Manager?

  1. Follow-on action recommendations
  2. Lessons Report
  3. Project closure notification
  4. Risk Register

Answer(s): B