Which of the following is NOT a trigger for the project manager to authorize a work package?

  1. Stage Authorization
  2. Corrective Action
  3. Exception plan approved
  4. Reporting highlights

Answer(s): D



Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

  1. Review the stage status
  2. Review work package status
  3. Report Highlights
  4. Take corrective action

Answer(s): C



During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?

  1. Team Plan
  2. Checkpoint Report
  3. Quality Register
  4. Configuration Item Record

Answer(s): C



During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

  1. Highlight report
  2. Checkpoint Report
  3. Issue Report
  4. End Stage Report

Answer(s): B