PRINCE2 Practitioner Practice Test & Exam Dumps
PRINCE2 Practitioner Questions 157–169 (page: 24)

Updated On: 10-Feb-2026
View Related Case Study

HOTSPOT
Column 1 is a list of actions that occur during the Controlling a Stage process. For each action in Column 1, select from Column 2 the PRINCE2 theme that is being applied. Each selection from Column 2 can be used once, more than once or not at all.
Drop down the answer from column 1 to column 2.
Hot Area:
Exhibit A:



Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



View Related Case Study

At the end of initiation there is +1 week 1-2 weeks time tolerance for this project. Which statement is true?

  1. There can be no time tolerances for any of the stages.
  2. All of the project level time tolerance can be allocated to stage 2.
  3. The Stage Plan for stage 2 could create some additional project time tolerance by allowing no time tolerance in Team Plans.
  4. Additional time tolerance for the project could be found by adding extra resources without affecting other tolerances.

Answer(s): B



View Related Case Study

During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to finish three weeks later, which statement is correct?

  1. The tolerances stated in the Project Plan CANNOT be changed.
  2. The Executive needs to seek formal approval from corporate management to implement this change.
  3. The current project must close prematurely and be restarted with a new Project Plan, a new Business Case and new Risk Register.
  4. The revision of the Project Plan would have to wait until the end stage assessment of stage 2.

Answer(s): B



View Related Case Study

During stage 2, an early review of the photo design ideas from the Marketing department has highlighted the need for engineering machinery to be operating in the background during the photo sessions. This requires a change to the baselined Product Description for the photos. What action should the Project Manager take?

  1. Log the change in the Issue Register as a request for change.
  2. Raise an Exception Report to the Project Board.
  3. Revised the Product Description for the photos and issue it to the Engineering Manager to ensure that the machinery will be operating during the photo sessions.
  4. Include this requirement on the next Checkpoint Report to the photographer.

Answer(s): A



View Related Case Study

As the project approaches the end of stage 2, the Project Manager has requested a Product Status Account to ensure that all products are at their expected point of development. Although the list of customers has been quality reviewed, it has not been baselined because the Marketing department have not provided all of the prospective customers' details. What initial action should the Project Manager take?

  1. Delay producing the End Stage Report until the list of customers has been baselined.
  2. Raise an Exception Report to the Project Board to highlight the issue.
  3. Check the target sign-off date for the list of customers.
  4. Update the product status to baselined and obtain a commitment from the Marketing department to finish this work within the next few days.

Answer(s): C



Viewing page 24 of 58
Viewing questions 116 - 120 out of 328 questions


Post your Comments and Discuss PRINCE2 PRINCE2 Practitioner exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!