PRINCE2 Practitioner Practice Test & Exam Dumps
PRINCE2 Practitioner Questions 151–163 (page: 25)

Updated On: 10-Feb-2026
View Related Case Study

Whilst identifying the mailing costs for the calendars the Project Manager was surprised to find the costs could vary considerably depending on the size of the package and the delivery service used. For the purpose of this project, the Project Manager has selected an appropriate service but feels that a corporate standard for postage would have reduced the time and effort invested. It could reduce the company's overheads by up to £20k per year. How should the Project Manager record this observation within the project?

  1. Produce a project mandate, outlining the potential savings to be achieved by the introduction of a corporate standard.
  2. Make a note of the observation in the Daily Log to be transferred to a Benefits Review Plan at the end of the project.
  3. Record the observation in an Exception Report to the Project Board.
  4. Make an entry in the Lessons Log for future consideration by corporate management.

Answer(s): D



View Related Case Study

The team member collating the list of customers has now forecast that it will NOT be complete by the end of this stage as originally planned, due to a number of new prospective customers' details not yet being available. What action should the team member take?

  1. Report the forecast delay in the next Checkpoint Report to the Executive.
  2. Add the product to the next Stage Plan in order to allocate additional resources and complete the work.
  3. Make an entry in the Risk Register so the Project Manager can decide on appropriate action.
  4. Raise an issue to inform the Project Manager.

Answer(s): D



View Related Case Study

HOTSPOT
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement For each line identify the appropriate option, from options 1 to 6, that applies. Each option can be used once, more than once or not at all.
Hot Area:
Exhibit A:



Exhibit B:

  1. Please refer to Exhibit B for answer.

Answer(s): A



Which of the following is the definition for an off-specification?

  1. An issue the Project Manager needs to resolve or escalate
  2. Something forecast or currently not meeting specification
  3. A proposal for a change to a baseline
  4. A statement of concern

Answer(s): B



In which strategy would the change control process be recorded?

  1. Quality Management Strategy
  2. Configuration Management Strategy
  3. Risk Management Strategy
  4. Communication Management Strategy

Answer(s): B



Viewing page 25 of 58
Viewing questions 121 - 125 out of 328 questions