During which process would the stage tolerances be set?

  1. Controlling a Stage
  2. Initiating a Project
  3. Managing a Stage Boundary
  4. Directing a Project

Answer(s): D



View Related Case Study

Which of the following is not a factor to consider when determining the length of a stage?

  1. The amount of resources available h the short term
  2. How far ahead you can sensibly plan n detail
  3. The technical stages within the project
  4. The amount of risk associated with the project

Answer(s): A



View Related Case Study

Which statement is TRUE with regard to technical stages?

  1. Technical stages can only occur sequential
  2. Technical stages define where management decisions are appropriate
  3. Technical stages often overlap
  4. Technical stages define the commitment of resources and authority to spend

Answer(s): C



View Related Case Study

There are two time driven controls in PRINCE2, which are they?

  1. Highlight and End Stage Reports
  2. Highlight and Checkpoint Reports
  3. Checkpoint and End Project Reports
  4. Highlight and Lessons Reports

Answer(s): B