PRINCE2 Practitioner Practice Test & Exam Dumps
PRINCE2 Practitioner Questions 146–150 (page: 27)

Updated On: 10-Feb-2026
View Related Case Study

According to PRINCE2, which statement about appointing the MFH Quality Manager to administer the configuration management procedure is correct?

  1. The MFH Quality Manager should administer the configuration management procedure on this project because this task should always be assigned to corporate or programme management.
  2. The MFH Quality Manager should only administer the configuration management procedure on one project at a time. If the MFH Quality Manager already performs this task on another project, another individual should be appointed.
  3. The MFH Quality Manager would be suitable to perform this task because he is the author of the document control process and is likely to have the knowledge required for this role.

Answer(s): C



View Related Case Study

Having created the Issue Report and analyzed the impact of removing the Facilities Division from the scope of the Outsourcing project, the proposed option exceeds tolerance. \Nhat is the next action the Project Manager should consider?

  1. Create an Exception Report to inform the Project Board of the situation and the available options.
  2. Update the associated Configuration Item Records with details of the Issue Report that caused the change.
  3. Amend the Stage Plan for stage 3: remove all products related to the Facilities Division and add the activities required to deliver the new Government initiative.
  4. Create an Exception Plan to change all of the project's products to reflect the exclusion of services provided by the Facilities Division.

Answer(s): A



View Related Case Study

What products will be impacted by this change?

  1. All of the project's products created so far.
  2. Only those products created in the first three weeks of stage 3.
  3. All of the project's products which relate to or include services provided by the Facilities Division.
  4. No products would need to be changed but some will need to be removed from the project.

Answer(s): D



View Related Case Study

What additional risk will this place on the project?

  1. None because risks associated with the centralization and rationalization of the Facilities Division will be managed by another project.
  2. These changes will delay stage 3 by three weeks.
  3. There is only £70k left in the project change budget.
  4. The reduced value of the contracted services required by the Outsourcing project may result in an insufficient number of proposals being received.

Answer(s): A



View Related Case Study

What will be the impact on the benefits?

  1. Reduced savings, now £10m over 10 years.
  2. Increased savings of £5m over 10 years from the new initiative to centralize the services provided by the Facilities Division.
  3. An additional cost of £1.5m to deliver the services provided by the Facilities Division.
  4. Outsourcing project cost reduced by 50%.

Answer(s): A



Viewing page 27 of 58
Viewing questions 131 - 135 out of 328 questions


Post your Comments and Discuss PRINCE2 PRINCE2 Practitioner exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!