This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Timing of communication activities section?

  1. Delete entry 9 because activities for controlling the project should be planned as part of Project controls in the Project Initiation Documentation.
  2. No change to entry 9 because it describes the timing of performance reports.
  3. Delete entry 10 because Highlight Reports are a Project Board control, the frequency of which should be recorded in the Project controls section of the Project Initiation Documentation.

Answer(s): B



View Related Case Study

This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Stakeholder analysis: Interested parties section?

  1. Add 'Internal Creative Team'.
  2. Delete entry 11 because the photographer is internal to the project management team.
  3. Delete entry 12 because the printing of the calendars is outside of the scope

Answer(s): A



View Related Case Study

This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
Which statement applies to the Information needs for each interested party section?

  1. Delete entry 13 because the activity to provide the weekly updates should be scheduled in the relevant Stage Plan.
  2. Move entry 13 to Tools and techniques because it describes the method to be used to communicate to the individual producing the staff newsletter.
  3. Delete entry 14 because this relates to the development of a particular product and should be recorded under Development interfaces within the relevant Work Package.

Answer(s): C



View Related Case Study

If Project tolerances were threatened, who needs to be notified?

  1. Project Board
  2. Project Manager
  3. Corporate or Programme Management
  4. Executive

Answer(s): C