If the Project Board are too busy to authorize all change requests themselves they can appoint?

  1. A Change Authority
  2. A Change Board
  3. A Change Committee
  4. A Change Budget

Answer(s): C



What is the purpose of a Product Status Account?

  1. A set of records that describe information about the project
  2. A log used to record problems or concerns about products
  3. An audit or review to compare actual status of products
  4. A report covering the status about the state of the projects products within

Answer(s): D



When examining a project issue, which three aspects should be considered?

1. Performance targets
2. Business Case
3. Resources
4. Risk

  1. 1,3,4
  2. 2,3,4
  3. 1,2,4
  4. 1,2,3

Answer(s): C



Who would be responsible for maintaining the Configuration Item Records?

  1. Project Manager
  2. Project Support
  3. Project Assurance
  4. Team Manager

Answer(s): B



View Related Case Study

According to PRINCE2, which statement about the Configuration Management Strategy for the Outsourcing project is correct?

  1. Every project needs a Configuration Management Strategy, even if the organization has existing configuration management standards, because every project has different circumstances.
  2. A separate Configuration Management Strategy will be required for each of the suppliers within this project because each will have a different way of managing and storing products.
  3. A Configuration Management Strategy is unnecessary for this project because the MFH document control process is documented. It is acceptable simply to reference this in the Quality Management Strategy.

Answer(s): A