SAP C_TSCM42_67 Exam
SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 (Page 3 )

Updated On: 12-Jan-2026

Which options can you offer someone who uses the SAP ECC system for production orders and requires support for material supply in production? (Choose three.)

  1. Automatic generation of a transport order
  2. Material directory
  3. Pull list
  4. Pick list
  5. Logistics Information System (LIS)

Answer(s): A,C,D



Which activity can trigger an automatic availability check for the components of a production order?

  1. Material staging
  2. Order rescheduling
  3. Order release
  4. Goods receipt for a missing part

Answer(s): C



In your company planning strategies are used in the SAP-ECC demand management that are based on consumption.
Which of the following statements about consumption is true?
(Choose two.)

  1. A consumption situation is dynamic and is always restructured with the planning run.
  2. Consumption can also take place between order reservations and planned independent requirements, depending on the strategy.
  3. Consumption always takes place on the material level between the planned independent requirements and the planned orders.
  4. The consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.

Answer(s): B,D



Which of the following elements do you have to prepare for costing of a production order to function without errors? (Choose three.)

  1. Assign costing variants to order type.
  2. Propose a standard text key in work center.
  3. Assign a production scheduling profile to the material master (product).
  4. Enter formulas for costing in the work center.
  5. Use an operation control key with the indicator costing-relevant.

Answer(s): A,D,E



The master data for an in-house production process is to be set up in the SAP ECC system. To do this, you should create a suitable routing that plans for five operations in an initial sequence (10, 20, 30, 40, 50). There should be an option of relocating operations 30 and 40 to a second sequence on other work centers if there are capacity bottlenecks. What sequence type would you use to create the second sequence in the system?

  1. Substitute sequence
  2. Alternative sequence
  3. Parallel sequence
  4. Standard sequence

Answer(s): B



Viewing page 3 of 23
Viewing questions 11 - 15 out of 106 questions