A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)

  1. Impediments are raised and resolved more slowly.
  2. Opportunities to inspect and adapt the Sprint Backlog are reduced.
  3. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
  4. The Scrum Master loses the ability to update the burndown chart adequately.
  5. The Product Owner cannot accurately inspect utilization of the individual team members.

Answer(s): A,B,C

Explanation:

The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint Goal.
Every day, the Development Team should understand how it intends to work together as a self-organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.



Steven is a Scrum Master asked to assist in creating five new Scrum Teams that will be working to build a highly anticipated product. He talks with them about the importance of being able to integrate their Increments by the end of their Sprints. This includes the first Sprints. The product is very important to both the end users and the organization.
Of the choices raised by future team members, what would Steven encourage?

  1. Each Scrum Team delivers Increments in its own code branch. After UAT is performed at the Sprint Review, the code branch is isolated until enough Increments are considered acceptable. All code branches will then be merged during the release phase.
  2. Each Scrum Team delivers functionality at the end of each Sprint. New Product Backlog items will then be added to the next Sprint Backlog to integrate their functionality with the other teams to create a unified Increment.
  3. All Scrum Teams agree on a mutual understanding of ‘done’ that defines all work necessary to deliver a potentially shippable Increment that includes all previous Increments delivered for the product.
  4. Wait until enough of the infrastructure and architecture is in place before starting the first Sprints. This will increase the success of delivering integrated Increments in Sprint 1.

Answer(s): C

Explanation:

When a Product Backlog item or an Increment is described as “Done”, everyone must understand what “Done” means. If there are multiple Scrum Teams working on the system or product release, the Development Teams on all the Scrum Teams must mutually define the definition of “Done” tohave a shared understanding of what it means for work to be complete, to ensure transparency. Each Increment is additive to all prior Increments and thoroughly tested, ensuring that all Increments work together.



According to the values of Scrum, which is the best way to create Development Teams?

  1. The Product Owner will create a skills matrix according to what is needed for the project and work with the technical leads to allocate resources to the team.
  2. Work with the leadership team to allocate members according to skills, seniority and experience to ensure that all Development Teams are balanced fairly.
  3. Provide boundaries to the developers and allow them to self-organize into Development Teams.

Answer(s): C

Explanation:

When the values of commitment, courage, focus, openness and respect are embodied and lived by the Scrum Team, the Scrum pillars of transparency, inspection, and adaptation come to life and build trust for everyone and self- organizing teams will be enabled to choose how best to accomplish their work.



When multiple Scrum Teams are working from the same Product Backlog, also known as scaled Scrum, they must still work in conformance of the Scrum guide.

  1. True
  2. False

Answer(s): A

Explanation:

Scrum is a framework with built in flexibility to support multiple Scrum Teams working on a single product.