What is management’s role in Scrum?

  1. To provide the necessary environment and support needed as defined by the Scrum Guide by providing insights and resources that help the Scrum Teams continue moving forward.
  2. Identifying and removing people that are performing poorly.
  3. Monitoring skill levels of the Development Team.
  4. Monitoring the Development Team’s velocity.

Answer(s): A

Explanation:

Getting the support from the business side helps facilitate the changes that fosters empiricism, self-organization, bottom-up intelligence, and intelligent release of software.



What would likely happen if management only changed the organization’s current terminology to fit Scrum without the proper understanding and support of Scrum as defined in the Scrum Guide?

  1. Very little change will happen as the vocabulary in Scrum is specifically defined for implementing Scrum.
  2. The organization may not realize the real benefits of Scrum as there would be no real change on the way the teams work.
  3. Organizations may feel less stressed as the behaviors would remain familiar to management.
  4. All answers apply.

Answer(s): D

Explanation:

The defined terminology in Scrum was selected, designed, and defined specifically for supporting the Scrum Framework. Understanding the differences between traditional methods and the Scrum Framework will help move teams in the right direction in Scrum adoption.



Which statement best describes Scrum?

  1. A clearly defined methodology that defines the software development process.
  2. A manual for defining best practices for software development.
  3. A clearly defined and predictable process that follows the principles of Computer Science.
  4. A framework to address complex products in complex environments.

Answer(s): D

Explanation:

Frameworks allow those closest to the problem the flexibility to creatively and productively deliver products of the highest possible value. Each component of Scrum serves a specific purpose and is essential to Scrum’s success and your usage of Scrum to develop complex projects.



In order to start the first Sprint, Scrum only requires a Product Owner with enough ideas, a Development Team to execute on those ideas, and a Scrum Master to guide the process.

  1. True
  2. False

Answer(s): A

Explanation:

In complex domains, you are only able to know the outcomes in hindsight. Empiricism, from which Scrum was founded on, asserts that knowledge comes from experience and making decisions based on what is known. New knowledge will emerge as work is being done.