Which of the following statements about scheduling is false?

  1. Defines the sequence of activities.
  2. Considers work calendars and time contingency.
  3. Provides a baseline for safety considerations.
  4. Quantifies the required resources.

Answer(s): C



Which of the following defines the term 'deployment baseline'?

  1. The starting point for creating a resource histogram.
  2. The basis for creating an organisational breakdown structure.
  3. The starting point for the monitoring of project risks.
  4. The basis for progress monitoring.

Answer(s): D



Which of the following is an activity in a typical configuration management process?

  1. Evaluation.
  2. Identification.
  3. Registration.
  4. Justification.

Answer(s): B



Stakeholder analysis supports effective stakeholder engagement by:

  1. identifying stakeholders with high levels of power and interest.
  2. ensuring stakeholder acceptance of project deliverables.
  3. justifying the preferred project option to stakeholders.
  4. providing information to all stakeholders.

Answer(s): A



Which of the following is a project?

  1. Introducing a new information technology system.
  2. Operating a national rail network.
  3. Organising ongoing catering in the armed forces.
  4. Managing day-to-day security for senior politicians

Answer(s): A