Free APM APM-PFQ Exam Questions (page: 8)

Which of the following actions would not help a team leader influence the performance of their team?

  1. Creating an exclusive environment.
  2. Providing clear roles and responsibilities.
  3. Promoting openness and honesty.
  4. Developing a trusting relationship.

Answer(s): A



One difference between a project and business as usual is:

  1. projects achieve specified benefits but business as usual has only vague benefits.
  2. projects drive change whereas business as usual continues existing activities.
  3. projects have tightly controlled budgets whereas business as usual does not.
  4. projects have unclear deadlines but business as usual has multiple milestones

Answer(s): B



The purpose of project progress reporting is to:

  1. ensure a simpler critical path.
  2. enable the tracking of project deliverables.
  3. ensure stakeholder acceptance of project deliverables.
  4. provide an increased total float.

Answer(s): B



Which of the following is the purpose of an estimating funnel?

  1. Keeping resource usage to a minimum to help reduce costs.
  2. Supporting the production of comparative estimates.
  3. Identifying where costs can be minimised when preparing a budget.
  4. Representing increasing levels of estimating accuracy achieved through the life cycle

Answer(s): D



One advantage of virtual communications is:

  1. that nonverbal signals can have an impact on discussions.
  2. it's easy to detect signs of conflict within the project team.
  3. access to a wider resource pool for the project.
  4. that the project team will always be co-located.

Answer(s): C