Who owns the Project Management Plan (PMP)?

  1. The project team.
  2. The chief executive.
  3. The project manager.
  4. The project support office

Answer(s): B



Which one of the following best describes users?

  1. Providers of both strategic and tactical direction to the project.
  2. Those intended to receive benefits or operate outputs.
  3. Facilitators of an appropriate issue resolution procedure.
  4. Those providing full-time commitment to the project.

Answer(s): B



Which statement best describes a responsibility of the project manager:

  1. to be the sole source of expertise for estimating techniques on cost and time.
  2. to deliver the project objectives to enable benefits to be realised.
  3. to take ultimate accountability for the delivery of the business benefits.
  4. to delegate all accountability for managing time, cost and quality to team leaders

Answer(s): B



A project is typically defined in terms of scope, time, cost and which other parameter?

  1. Benefits.
  2. Quality.
  3. Tolerance.
  4. Controls.

Answer(s): D



Which one of the following statements is true?

  1. Business-as-usual activities cannot be improved.
  2. Business-as-usual activities are more difficult to manage than projects.
  3. Projects are transient endeavours that bring about change to business-as-usual.
  4. A project is always the starting point for operation refinement.

Answer(s): C