One purpose of a typical project business case is to:

  1. carry out earned value analysis.
  2. allocate resources to the project.
  3. analyse cost-benefit of the project.
  4. plan project work packages

Answer(s): C



One disadvantage of physical communication is:

  1. its significant environmental impact when compared to other forms of communication.
  2. that no audit trail is available for review at a later date by project team members.
  3. it is reliant on technology being available to all relevant members of the project.
  4. that your body language may not reflect what you're saying when passing on information

Answer(s): A



One of the benefits of developing communication plans in projects is that this ensures:

  1. the power and influence of stakeholders is understood.
  2. that all communication is delivered face to face.
  3. your message is understood.
  4. clear reporting lines for the project.

Answer(s): C



A project life cycle which combines approaches from the linear and iterative life cycles is known as _________ project life cycle.

  1. a hybrid.
  2. an extended.
  3. a reduced.
  4. a combined.

Answer(s): A



The purpose of project management is to:

  1. organise management plans.
  2. keep all stakeholders happy.
  3. control change initiatives.
  4. effect beneficial change.

Answer(s): D