One aspect of quality planning is to:

  1. plan the audit of a project to provide assurance to the project board.
  2. provide confidence that a project will achieve its objectives in the required time frame.
  3. specify the acceptance criteria used to validate the outputs are fit for purpose.
  4. confirm routes for reporting to ensure effective communication

Answer(s): C



Which of the following is not a key element of project scope management?

  1. Define outputs.
  2. Identify outputs.
  3. Share outputs.
  4. Control outputs

Answer(s): C



Which of the following is a difference between deployment baselines in linear life cycles and iterative life cycles?

  1. Linear project life cycles set the deployment baseline for the whole project.
  2. In an iterative project life cycle the scope and quality are fixed in the deployment baseline.
  3. Only deployment baselines in iterative life cycles have an integrated baseline review.
  4. Only deployment baselines in linear life cycles have an integrated baseline review

Answer(s): A



Which of the following defines the term 'risk'?

  1. The potential of a situation or event to impact on the achievement of specific objectives.
  2. A problem that is now or is about to breach delegated tolerances for work on a project or programme.
  3. Scope creep within an uncontrolled project.
  4. The use of estimation to determine costs, resources and activities.

Answer(s): A



Suppliers are stakeholders of a project management plan because they:

  1. contribute to the project's procurement strategy.
  2. help satisfy the project's resource requirements.
  3. provide acceptance certificates based on quality of resources supplied.
  4. determine the quality requirements of goods supplied.

Answer(s): B