Which of the following defines the term 'issue'?

  1. A problem which is now or is about to breach delegated tolerances for work on a project or programme.
  2. A problem which occurs on a day-to-day basis which could have an immediate impact on a project.
  3. A problem which has the potential to impact on the achievement of specific project objectives.
  4. A problem which can only be resolved by a project manager and within the project team

Answer(s): A



Which of the following define leadership?
1) Ability to establish vision and direction
2) Developing team skills that enhance project performance3) Empowering and inspiring people to achieve success
4) Ability to influence and align others towards a common purpose

  1. 1, 2 & 4
  2. 1, 2 & 3
  3. 2, 3 & 4
  4. 1, 3 & 4

Answer(s): D



Which of the following are typical estimating methods? 1) Analytical 2) Budgeting 3) Analogous 4) Parametric

  1. 1, 2 and 4
  2. 1, 2 and 3
  3. 1, 3 and 4
  4. 2, 3 and 4

Answer(s): C



Procurement strategy can be defined as the high-level approach for securing:

  1. stakeholder engagement.
  2. funding for the project.
  3. buy in from the project sponsor.
  4. goods and services required for the project.

Answer(s): D



Which of the following is not an output of a critical path analysis?

  1. Total and free float.
  2. Earliest start time and latest finish time of activities.
  3. Project completion time.
  4. Cost-benefit analysis.

Answer(s): D