Which one of the following does project change control primarily seek to ensure?

  1. All variance to the project scope is evaluated.
  2. No reduction in the perceived quality of the project outcome.
  3. Management costs of the project do not increase.
  4. Any decrease in the scoped deliverable of the project is rejected.

Answer(s): A



Which one of the following is captured in the Work Breakdown Structure (WBS)?

  1. The life cycle phases.
  2. The logical order of tasks.
  3. The scope of the project.
  4. Project costs.

Answer(s): C



Project reporting can best be defined as:

  1. informing stakeholders about the project.
  2. storing and archiving of project information.
  3. gathering stakeholder feedback.
  4. collecting project information.

Answer(s): A



Which one of the following statements best defines an estimate?

  1. An approximation of project time and cost targets, refined throughout the project life cycle.
  2. A prediction of a future condition or event based on information or knowledge available now.
  3. The value of useful work done at any given point in a project to give a measure of progress.
  4. A situation that affects or influences the outcome of the project expressed in time or cost term

Answer(s): A



Which one of the following is a responsibility of the project steering group/board?

  1. To identify potential problems for the project team to solve.
  2. To provide strategic direction and guidance to the sponsor.
  3. To manage the project team in all daily activities.
  4. To receive and consider daily reports from team members.

Answer(s): B