When is an analysis of a project's environment most likely to be undertaken?

  1. In the Definition Phase
  2. In the Transition Phase
  3. In the Concept Phase
  4. In the Deployment Phase

Answer(s): C



Which one of the following statements BEST defines procurement?

  1. A technique to establish the best approach for obtaining the resources for the project
  2. A group of interrelated resources and activities that transform inputs into outputs
  3. The description of the purpose, form and components to support delivery of a product
  4. The process by which products and services required for the project are acquired

Answer(s): D



Which of these is likely to occur if the scope is poorly defined?
1. Additional time spent in the concept phase
2. Scope creep
3. Budget over/under runs
4. Scheduling problems

  1. 1, 2 and 3
  2. 1, 2 and 4
  3. 1, 3 and 4
  4. 2, 3 and 4

Answer(s): D



Which of the following is included in a Procurement Strategy?

  1. Benefits
  2. Stakeholder list
  3. Contract pricing information
  4. Specification of works

Answer(s): C



A review undertaken to decide whether a project should proceed into its next phase is known as a...

  1. decision gate.
  2. feasibility study.
  3. milestone review.
  4. evaluation review.

Answer(s): A