What would be the effect if the resources required for a project's critical path activities were insufficient?

  1. It would reduce the project duration.
  2. It would extend the project duration.
  3. The quality of the deliverables would suffer.
  4. Resource smoothing should be applied to the critical path.

Answer(s): B



Which one of the following is the best description of project scope?

  1. Scope is detailed in the business case.
  2. Scope is the total work content of a project.
  3. Scope is an outcome of the scheduling and estimating processes.
  4. Scope defines what is NOT delivered by the project.

Answer(s): B



When delivering a project the Project Manager has to balance which one of the following constraints:

  1. definition and delivery.
  2. time, cost and quality.
  3. cost and scope.
  4. budget, spend and contingency

Answer(s): B



Which one of the following statements is true?

  1. Business-as-usual activities cannot be improved.
  2. Business-as-usual activities are more difficult to manage than projects.
  3. Projects are transient endeavours that bring about change to business-as-usual.
  4. A. project is always the starting point for operational refinement.

Answer(s): C



What is the purpose of a stakeholder grid?

  1. A means of stakeholder identification.
  2. It provides a statement of the stakeholder communications plan.
  3. To understand a stakeholder's position in relation to the project.
  4. It presents an action plan for stakeholder management.

Answer(s): C