APM Project Fundamentals Qualification Questions 186–190 (page: 39)

Updated On: 10-Feb-2026

Which one of the following takes place during closeout?

  1. Benefits realisation review.
  2. Final project review.
  3. Deliverables accepted by sponsor.
  4. Handover of relevant documentation

Answer(s): B



Which statement best describes a responsibility of the project team members?

  1. To establish formal reporting procedures for project progress.
  2. To assess the progress of their work against the strategic objectives.
  3. To ensure that work assigned to them by the Project Manager is performed.
  4. To identify and resolve project issues affecting the work delegated to them

Answer(s): C



The role of a leader includes:

  1. effectively managing risks.
  2. selecting the project team.
  3. coaching and mentoring project staff.
  4. producing accurate project reports.

Answer(s): C



The primary purpose of a gate review is to decide:

  1. whether the project manager and team are performing well.
  2. if the project is on schedule and within budget.
  3. if stakeholders are satisfied.
  4. whether to continue with the project.

Answer(s): D



The primary purpose of the post-project review is to:

  1. find out who was responsible for problems on the project and why.
  2. find out whether the business benefits were achieved and why.
  3. find out who performed well on the project in order to support future resource allocations.
  4. identify lessons learned to enable continuous improvement.

Answer(s): D



Viewing page 39 of 83
Viewing questions 191 - 195 out of 354 questions