Which of the following is not a stage in an issue resolution process?

  1. Share the issue with stakeholders.
  2. Track the issue to closure.
  3. Escalate to the sponsor.
  4. Apply change control.

Answer(s): A



Which of the following are challenges for a project manager developing and leading a project team?
1) Issues and incompatibility amongst team members
2) Getting the right skills and attributes amongst team members
3) Co-location of team members in the same geographic area
4) Lack of accountability of team members

  1. 1, 2 & 3
  2. 1, 2 & 4
  3. 1, 3 & 4
  4. 2, 3 & 4

Answer(s): C



Which of the following is an activity in a typical change control process?

  1. Recommendation.
  2. Justification.
  3. Planning.
  4. Continuous improvement

Answer(s): A



The purpose of quality assurance is to:

  1. provide confidence the project will satisfy the relevant quality standards.
  2. determine a set of procedures and standards for project management.
  3. inspect, measure and test deliverables and processes.
  4. define the scope and specifics of a project's deliverables

Answer(s): A



A project manager might use a PESTLE analysis in order to:

  1. mitigate all possible risks to the project.
  2. identify and mitigate factors that may affect the project.
  3. control technological change during the project.
  4. consider team social roles in early stages of the project

Answer(s): B