Which of the following are phases in an iterative project life cycle? 1) Concept 2) Feasibility 3) Deployment 4) Development

  1. 3 and 4 only
  2. 1, 2 and 3
  3. 1 and 2 only
  4. 2, 3 and 4

Answer(s): D



Which of the following is the responsibility of a project manager?

  1. Ensuring a project is aligned to the organisation's strategy.
  2. Focusing on project benefits and aligning priorities.
  3. Achieving the project's success criteria.
  4. Improving process, tools and techniques used in a project

Answer(s): C



To develop and establish a proper communication plan within a project, the project manager needs to consider which type of analysis?

  1. Budget.
  2. Stakeholder.
  3. Resource.
  4. Schedule

Answer(s): B



Which of the following is a responsibility of the project sponsor?

  1. Creating a project cost breakdown structure.
  2. Authoring the project management plan.
  3. Creating a project work breakdown structure.
  4. Owning the project business case.

Answer(s): D



Portfolio management includes prioritising:

  1. projects and/or programmes that contribute directly to the organisation's strategic objectives.
  2. projects with exceptionally high returns on investment.
  3. projects and programmes over business as usual.
  4. projects which maximise change over those which maximise investment

Answer(s): A