A customer has requested additional features for an active project. Which of the following steps should take place NEXT?

  1. Implement the requested changes.
  2. Evaluate the impact of the changes.
  3. Update all project documents.
  4. Submit the requested changes to the CCB.

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293



A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success.

Which of the following risk strategies should the project manager adopt?

  1. Exploitation
  2. Avoidance
  3. Acceptance
  4. Mitigation

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 239



A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.

Which of the following documents should the project manager create?

  1. Business case
  2. Project charter
  3. Scope statement
  4. Project management plan

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107



Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

  1. Sales clerk
  2. Marketing representative
  3. Team lead
  4. Product item

Answer(s): B



Viewing page 16 of 182
Viewing questions 61 - 64 out of 1001 questions



Post your Comments and Discuss CompTIA PK0-004 exam prep with other Community members:

PK0-004 Exam Discussions & Posts