Which of the following are examples of organizational change? (Choose two.)

  1. Relocation
  2. Scope
  3. Business process
  4. Schedule
  5. Risk event

Answer(s): A,C


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297



A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?

  1. Project schedule
  2. Cost plan
  3. Scope statement
  4. Impact assessment

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156



A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few minutes to review the project.
Which of the following are critical for the project manager to provide?

  1. Cost, schedule, organizational chart, and risks/issues
  2. Risks/issues, cost, RACI chart, and action items
  3. Schedule, cost, risks/issues, and milestones
  4. Action items, organizational chart, schedule, and NDA

Answer(s): C


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326



During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.

Which of the following should have occurred to prevent this issue?

  1. During the planning phase, the project manager should have recognized the relationship between the vendor’s and project team’s tasks and adjusted the schedule for the project team to begin activities two months later.
  2. The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.
  3. During the project team’s regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.
  4. During the project team’s regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170



A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies. Which of the following documents should the project coordinator use?

  1. Risk register
  2. Issue log
  3. Communication plan
  4. Status report

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240